  "as_of": "2026-09-01",
  "table_prepared_at": "2026-08-28",
  "verified_on": "2026-11-13",
  "unit": "buildings",
  "publisher": "Loudoun County Department of Planning and Zoning",
  "source_page": "https://www.loudoun.gov/6408/Data-Centers-The-Loudoun-Story",
  "source_table": "https://www.loudoun.gov/DocumentCenter/View/222160",
  "source_dashboard": "https://www.loudoun.gov/6439/Data-Center-Dashboard",
  "source_dashboard_mirror": "https://sheriff.loudoun.gov/6439/Data-Center-Dashboard",
  "built_or_under_construction": {
    "buildings": 245,
    "sqft": 58333856
  },
  "approved_or_administrative_pipeline": {
    "buildings": 114,
    "sqft": 33837043,
    "approved_site_plans_no_building_permit": {
      "buildings": 47,
      "sqft": 14132966
    },
    "site_plans_in_administrative_review": {
      "buildings": 62,
      "sqft": 18463181
    },
    "legislatively_approved_no_site_plan": {
      "buildings": 5,
      "sqft": 1240896
    }
  },
  "pending_legislative_approval": {
    "buildings": 54,
    "sqft": 20959734
  },
  "notes": [
    "September 1, 2026 countywide counts are estimates: the 245 group combines buildings already built and under construction; it is not an operating-only count.",
    "The 114 in the approved/administrative pipeline includes 47 approved site plans without building permits, 62 site plans in review, and 5 legislatively approved buildings without site plans; this is not 114 fully permitted buildings.",
    "The 54 buildings in active legislative applications remain unapproved and are separate from the 114-building pipeline.",
    "The September 1 county narrative and status table do not state the number of active legislative applications. The previous March 1 edition cited 21; do not present 21 as a current September count.",
    "Countywide buildings and their square footage are separate from GIS mapped layer records, parcel IDs, project or campus counts, and old building outlines. Not all planned buildings will be constructed.",
    "The department table is dated September 1, 2026 and notes preparation on August 28, 2026. Counts reflect the county's source documents, permits, GIS and LandMARC and may be revised.",
    "The county moved its summary building counts from its Loudoun Story narrative to its Data Center Dashboard. As of November 19, 2026 the district PDF text extraction lists September figures while its rendered page visibly shows the March table. Dashboard and extracted table totals match September; visually correct republication from county is still needed. The source checker watches the dashboard and dated PDF link, not the unresolved PDF visual."
  ],
  "previous_snapshot": {
    "as_of": "2026-03-01",
    "built_or_under_construction": {
      "buildings": 233,
      "sqft": 56540000
    },
    "approved_or_administrative_pipeline": {
      "buildings": 116,
      "sqft": 35653000,
      "approved_site_plans_no_building_permit": {
        "buildings": 51,
        "sqft": 16201000
      },
      "site_plans_in_administrative_review": {
        "buildings": 58,
        "sqft": 16915000
      },
      "legislatively_approved_no_site_plan": {
        "buildings": 7,
        "sqft": 2537000
      }
    },
    "pending_legislative_approval": {
      "applications": 21,
      "buildings": 56,
      "sqft": 20702000
    }
  },
  "built_and_pipeline_total": {
    "buildings": 359,
    "sqft": 92170899
  }
}