X-WR-CALDESC:Every dated milestone in Loudoun County's data center record: 
 applications as they are filed\, and movements in the county's built and p
 roposed parcel layers. Loudoun Data Center Watch is an independent communi
 ty project. It is not affiliated with\, endorsed by\, or operated by Loudo
 un County government\, Erin Brockovich\, or any data center owner or opera
 tor.
BEGIN:VEVENT
UID:ldcw-case-bda97044aa19a4bb0101@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20261116
DTEND;VALUE=DATE:20261117
SUMMARY:New application — subdivision plat: Allegro North Campus - Buildi
 ng 2B-2E Site Plan\, Little River district
DESCRIPTION:Subdivision plat PLAT-2026-0169\, filed with Loudoun County on 
 16 November 2026. The county's current status for it is Submitted. Located
  in the Little River district\, worked out from the coordinates the county
  publishes with the case against data/districts.geojson. The applicant's o
 wn description: EASEMENT PLAT FOR ALLEGRO NORTH CAMPUS - BLDG 2B-2E: The S
 ite Plan is for Buildings 2B-2E of the North Campus of a data center compl
 ex with associated support facilities. Source: Loudoun County land develop
 ment case list\, https://logis.loudoun.gov/gis/rest/services/Projects/LOLA
 _DATA/MapServer/0\, via data/activity.json. Loudoun Data Center Watch is a
 n independent community project. It is not affiliated with\, endorsed by\,
  or operated by Loudoun County government\, Erin Brockovich\, or any data 
 center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/b2f0a352
 -afde-4ef5-917c-934be1dfc8bc
CATEGORIES:Subdivision plat
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-5d6831197ff0996089e4@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20261116
DTEND;VALUE=DATE:20261117
SUMMARY:New application — site plan: LC4 Data Center SPAM2\, Sterling dis
 trict
DESCRIPTION:Site plan EPLAN-2026-0182\, filed with Loudoun County on 16 Nov
 ember 2026. The county's current status for it is Submitted - Online. Loca
 ted in the Sterling district\, worked out from the coordinates the county 
 publishes with the case against data/districts.geojson. The applicant's ow
 n description: THIS SPAM IS FOR THE REVISION TO THE APPROVED SPAM-2023-003
 2.  REVISIONS INCLUDE THE REMOVAL OF THE PREVIOUSLY PROPOSED GUARD SHACK A
 ND ASSOCIATED DETAILS.  THE TOTAL CUMULATIVE GFA FOR LC4A/LC4B HAS NOT CHA
 NGED.  THERE ARE NO CHANGES TO THE SWM PLAN\, TREE CONSERVATION AREAS OR L
 ANDSCAPE PLAN WITH T Source: Loudoun County land development case list\, h
 ttps://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/0\
 , via data/activity.json. Loudoun Data Center Watch is an independent comm
 unity project. It is not affiliated with\, endorsed by\, or operated by Lo
 udoun County government\, Erin Brockovich\, or any data center owner or op
 erator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/5b456fa2
 -f9f3-4b4f-8452-ac8f7c196395
CATEGORIES:Site plan
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-34b4a513150c38789053@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20261111
DTEND;VALUE=DATE:20261112
SUMMARY:New application — site plan: Ashburn North Phase 2 - DC12 Buildin
 g\, Broad Run district
DESCRIPTION:Site plan EPLAN-2026-0178\, filed with Loudoun County on 11 Nov
 ember 2026. The county's current status for it is Submitted - Online. Loca
 ted in the Broad Run district\, worked out from the coordinates the county
  publishes with the case against data/districts.geojson. The applicant's o
 wn description: SPAM submission to add a proposed reclaim water filtration
  system to the DC-12 Building in Ashburn North Phase 2. System is proposed
  within existing parking area and revisions also include landscaping chang
 es. Data Center Source: Loudoun County land development case list\, https:
 //logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/0\, via
  data/activity.json. Loudoun Data Center Watch is an independent community
  project. It is not affiliated with\, endorsed by\, or operated by Loudoun
  County government\, Erin Brockovich\, or any data center owner or operato
 r.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/17300968
 -256f-4362-9eb9-9d4979bf3ff8
CATEGORIES:Site plan
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-74654b854f497f669302@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20261110
DTEND;VALUE=DATE:20261111
SUMMARY:New application — zoning determination: Allegro North Parcel 2A\,
  Little River district
DESCRIPTION:Zoning determination ZCOR-2026-0343\, filed with Loudoun County
  on 10 November 2026. The county's current status for it is In Review. Loc
 ated in the Little River district\, worked out from the coordinates the co
 unty publishes with the case against data/districts.geojson. The applicant
 's own description: Lauren Hrebenak of Curata Partners PLLC is requesting 
 a zoning verification confirming that data center uses are permitted on th
 e Property by-right pursuant to the conditionally approved site plan\, All
 egro North Campus - BLDG 2A\, (EPLAN-2023-0104) Source: Loudoun County lan
 d development case list\, https://logis.loudoun.gov/gis/rest/services/Proj
 ects/LOLA_DATA/MapServer/0\, via data/activity.json. Loudoun Data Center W
 atch is an independent community project. It is not affiliated with\, endo
 rsed by\, or operated by Loudoun County government\, Erin Brockovich\, or 
 any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/2df548eb
 -1389-431b-8b42-bbb655c8af1b
CATEGORIES:Zoning determination
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-1856ece0fda163fa4ea8@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20261110
DTEND;VALUE=DATE:20261111
SUMMARY:New application — site plan: Intergate Ashburn Building 'A'\, Bro
 ad Run district
DESCRIPTION:Site plan EPLAN-2026-0176\, filed with Loudoun County on 10 Nov
 ember 2026. The county's current status for it is Submitted - Online. Loca
 ted in the Broad Run district\, worked out from the coordinates the county
  publishes with the case against data/districts.geojson. The applicant's o
 wn description: A site plan amendment to STMP-2022-0011. This project prop
 oses revisions to the utility yard and the addition of the adiabatic syste
 m. Data Center Source: Loudoun County land development case list\, https:/
 /logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/0\, via 
 data/activity.json. Loudoun Data Center Watch is an independent community 
 project. It is not affiliated with\, endorsed by\, or operated by Loudoun 
 County government\, Erin Brockovich\, or any data center owner or operator
 .
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/0a4fe3df
 -19e3-4d13-a4b6-46bdcde01fea
CATEGORIES:Site plan
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-b4c0e3529e23af630482@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20261106
DTEND;VALUE=DATE:20261107
SUMMARY:New application — performance bond release: LOUDOUN CENTER - LOT 
 1\, ASH 2\, Leesburg district
DESCRIPTION:Performance Bond Release PBORE-2026-0024\, filed with Loudoun C
 ounty on 6 November 2026. The county's current status for it is In Review.
  Located in the Leesburg district\, worked out from the coordinates the co
 unty publishes with the case against data/districts.geojson. The applicant
 's own description: LOUDOUN CENTER - LOT 1\, ASH 2 DATA CENTER - STMP-2018
 -0003 Revised by SPAM-2020-0061 -AGED -Stays w/ BMT (9-22-26) Source: Loud
 oun County land development case list\, https://logis.loudoun.gov/gis/rest
 /services/Projects/LOLA_DATA/MapServer/0\, via data/activity.json. Loudoun
  Data Center Watch is an independent community project. It is not affiliat
 ed with\, endorsed by\, or operated by Loudoun County government\, Erin Br
 ockovich\, or any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/3ccaf6df
 -5f3b-4b8e-94ae-556f8996fdf2
CATEGORIES:Performance Bond Release
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-fb6545e9f18822513d90@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260917
DTEND;VALUE=DATE:20260918
SUMMARY:New application — site plan: Cross Mill Center\, Leesburg distric
 t
DESCRIPTION:Site plan EPLAN-2026-0140\, filed with Loudoun County on 17 Sep
 tember 2026. The county's current status for it is In Review. Located in t
 he Leesburg district\, worked out from the coordinates the county publishe
 s with the case against data/districts.geojson. The applicant's own descri
 ption: CROSS MILL CENTER - This plan proposes the development of two data 
 center buildings with associated infrastructure and construction of proffe
 red road improvmeents along Sycolin Road Source: Loudoun County land devel
 opment case list\, https://logis.loudoun.gov/gis/rest/services/Projects/LO
 LA_DATA/MapServer/0\, via data/activity.json. Loudoun Data Center Watch is
  an independent community project. It is not affiliated with\, endorsed by
 \, or operated by Loudoun County government\, Erin Brockovich\, or any dat
 a center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/07382ae4
 -0327-4810-8a27-a1e0b7c83b69
CATEGORIES:Site plan
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-e770f2931b0aa7ce0f92@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260916
DTEND;VALUE=DATE:20260917
SUMMARY:New application — subdivision plat: Tech Park at Dulles\, Dulles 
 district
DESCRIPTION:Subdivision plat PLAT-2026-0143\, filed with Loudoun County on 
 16 September 2026. The county's current status for it is In Review. Locate
 d in the Dulles district\, worked out from the coordinates the county publ
 ishes with the case against data/districts.geojson. The applicant's own de
 scription: Site plan for the construction of 3 Data Center buildings\, a w
 arehouse building\, and associated infrastructure Source: Loudoun County l
 and development case list\, https://logis.loudoun.gov/gis/rest/services/Pr
 ojects/LOLA_DATA/MapServer/0\, via data/activity.json. Loudoun Data Center
  Watch is an independent community project. It is not affiliated with\, en
 dorsed by\, or operated by Loudoun County government\, Erin Brockovich\, o
 r any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/099e54f2
 -ce32-43ce-b548-570400838e4f
CATEGORIES:Subdivision plat
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-3a580fae1e009450a8e6@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260828
DTEND;VALUE=DATE:20260829
SUMMARY:New application — site plan: American Square at Quantum C1 Upgrad
 es\, Broad Run district
DESCRIPTION:Site plan EPLAN-2026-0132\, filed with Loudoun County on 28 Aug
 ust 2026. The county's current status for it is In Review. Located in the 
 Broad Run district\, worked out from the coordinates the county publishes 
 with the case against data/districts.geojson. The applicant's own descript
 ion: Site Plan Amendment (SPAM) to SPAM-2019-0102 (Approved 04/22/2020)\n\
 nTHE INTENT OF THIS SITE PLAN AMENDMENT IS TO MODIFY THE EXISTING PARKING 
 LOT NORTH OF THE D2 BUILDING AND ADD MECHANICAL EQUIPMENT TO THE\nAREA. AD
 DITIONAL IMPROVEMENTS INCLUDE MODIFIED SIDEWALK CIRCULATION\, DRIVEWAY CIR
 CULATION\, AND Source: Loudoun County land development case list\, https:/
 /logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/0\, via 
 data/activity.json. Loudoun Data Center Watch is an independent community 
 project. It is not affiliated with\, endorsed by\, or operated by Loudoun 
 County government\, Erin Brockovich\, or any data center owner or operator
 .
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/3c74e794
 -50c6-4e01-9ae0-95fc14c33239
CATEGORIES:Site plan
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-592b7d430dc5bcf20fa2@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260825
DTEND;VALUE=DATE:20260826
SUMMARY:New application — subdivision plat: 110 Terminal Drive Data Cente
 r\, Sterling district
DESCRIPTION:Subdivision plat PLAT-2026-0130\, filed with Loudoun County on 
 25 August 2026. The county's current status for it is In Review. Located i
 n the Sterling district\, worked out from the coordinates the county publi
 shes with the case against data/districts.geojson. The applicant's own des
 cription: 110 TERMINAL DRIVE DATA CENTER Easement Plat: Easement plat for 
 offsite easements associated with EPLAN-2024-0105 Source: Loudoun County l
 and development case list\, https://logis.loudoun.gov/gis/rest/services/Pr
 ojects/LOLA_DATA/MapServer/0\, via data/activity.json. Loudoun Data Center
  Watch is an independent community project. It is not affiliated with\, en
 dorsed by\, or operated by Loudoun County government\, Erin Brockovich\, o
 r any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/463a1aab
 -f0e0-40e9-a27d-0a09968ec07d
CATEGORIES:Subdivision plat
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-1498ade2eb9c15f6580f@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260820
DTEND;VALUE=DATE:20260821
SUMMARY:New application — subdivision plat: 110 Terminal Drive Data Cente
 r\, Sterling district
DESCRIPTION:Subdivision plat PLAT-2026-0128\, filed with Loudoun County on 
 20 August 2026. The county's current status for it is In Review. Located i
 n the Sterling district\, worked out from the coordinates the county publi
 shes with the case against data/districts.geojson. The applicant's own des
 cription: 110 TERMINAL DRIVE DATA CENTER Easement Plat: Easement plat for 
 onsite easements associated with EPLAN-2024-0105 Source: Loudoun County la
 nd development case list\, https://logis.loudoun.gov/gis/rest/services/Pro
 jects/LOLA_DATA/MapServer/0\, via data/activity.json. Loudoun Data Center 
 Watch is an independent community project. It is not affiliated with\, end
 orsed by\, or operated by Loudoun County government\, Erin Brockovich\, or
  any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/32928c4e
 -a73d-4a79-854d-67cdfd1a4a22
CATEGORIES:Subdivision plat
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-e741cbd6914b561c7fac@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260817
DTEND;VALUE=DATE:20260818
SUMMARY:New application — zoning determination: 24141 Upper Woodside Ln D
 ETER\, Little River district
DESCRIPTION:Zoning determination ZCOR-2026-0256\, filed with Loudoun County
  on 17 August 2026. The county's current status for it is In Review. Locat
 ed in the Little River district\, worked out from the coordinates the coun
 ty publishes with the case against data/districts.geojson. The applicant's
  own description: Ben Wales of Curata Partners is requesting a zoning dete
 rmination for 24141 Upper Woodside Lane\, Sterling - PIN: 162-39-2026-000 
 if additional floor area can be added to an existing building on the Prope
 rty pursuant to Section 10.11.01.H.\n\nZoning determination request seekin
 g confirmation that an ex Source: Loudoun County land development case lis
 t\, https://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServ
 er/0\, via data/activity.json. Loudoun Data Center Watch is an independent
  community project. It is not affiliated with\, endorsed by\, or operated 
 by Loudoun County government\, Erin Brockovich\, or any data center owner 
 or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/a77c2508
 -1918-432b-977d-facc033a9fb5
CATEGORIES:Zoning determination
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-e802dfcbbd833f736a93@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260814
DTEND;VALUE=DATE:20260815
SUMMARY:New application — zoning determination: 45415 Leesburg Pike DETER
 \, Algonkian district
DESCRIPTION:Zoning determination ZCOR-2026-0246\, filed with Loudoun County
  on 14 August 2026. The county's current status for it is In Review. Locat
 ed in the Algonkian district\, worked out from the coordinates the county 
 publishes with the case against data/districts.geojson. The applicant's ow
 n description: Dr. Nathan B. Wangusi is requsting a zoning determination f
 or PINs: 039-47-4460\,\n039-37-0350\, 039-46-6559\, 039-45-6733\, 039-26-3
 557\, 039-16-8997\, 039-17-4565\, 057-40-9553\, if the following is an all
 owable use: data center as a  by-right use\, without an approved SPEX.\n\n
 Request for Written Zoning Dete Source: Loudoun County land development ca
 se list\, https://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/M
 apServer/0\, via data/activity.json. Loudoun Data Center Watch is an indep
 endent community project. It is not affiliated with\, endorsed by\, or ope
 rated by Loudoun County government\, Erin Brockovich\, or any data center 
 owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/50243df3
 -8eb9-4d91-9fbe-669a41d3f243
CATEGORIES:Zoning determination
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-c490be4a7eed71fab131@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260812
DTEND;VALUE=DATE:20260813
SUMMARY:New application — subdivision plat: Dulles Electric Data Centers 
 Consolidation\, Sterling district
DESCRIPTION:Subdivision plat PLAT-2026-0121\, filed with Loudoun County on 
 12 August 2026. The county's current status for it is In Review. Located i
 n the Sterling district\, worked out from the coordinates the county publi
 shes with the case against data/districts.geojson. The applicant's own des
 cription: Consolidation of 4 properties to support EPLAN-2024-0154. Source
 : Loudoun County land development case list\, https://logis.loudoun.gov/gi
 s/rest/services/Projects/LOLA_DATA/MapServer/0\, via data/activity.json. L
 oudoun Data Center Watch is an independent community project. It is not af
 filiated with\, endorsed by\, or operated by Loudoun County government\, E
 rin Brockovich\, or any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/309b3cf2
 -0583-42b8-8fd4-9ddc24abb84e
CATEGORIES:Subdivision plat
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-36087abf45273d2ffe67@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260811
DTEND;VALUE=DATE:20260812
SUMMARY:New application — site plan: AWS 42949 Fadeley Lane\, Little Rive
 r district
DESCRIPTION:Site plan EPLAN-2026-0116\, filed with Loudoun County on 11 Aug
 ust 2026. The county's current status for it is In Review. Located in the 
 Little River district\, worked out from the coordinates the county publish
 es with the case against data/districts.geojson. The applicant's own descr
 iption: The applicant requests approval for a minor addition to a principa
 l building on an approved Special Exception pursuant to Section 10.11.01.H
 .2. for a 14\,177-square-foot footprint addition to the existing data cent
 er facility (Building 081) at 42949 Fadeley Lane. The proposed minor addit
 ion to the ex Source: Loudoun County land development case list\, https://
 logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/0\, via d
 ata/activity.json. Loudoun Data Center Watch is an independent community p
 roject. It is not affiliated with\, endorsed by\, or operated by Loudoun C
 ounty government\, Erin Brockovich\, or any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/83485c36
 -104f-44ea-a5f4-399612fd1484
CATEGORIES:Site plan
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-760a0e40ba5d3fcdf39f@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260729
DTEND;VALUE=DATE:20260730
SUMMARY:New application — site plan: Twin Creeks Buildings 1-3\, Leesburg
  district
DESCRIPTION:Site plan EPLAN-2026-0111\, filed with Loudoun County on 29 Jul
 y 2026. The county's current status for it is In Review. Located in the Le
 esburg district\, worked out from the coordinates the county publishes wit
 h the case against data/districts.geojson. The applicant's own description
 : Project proposing Data Center buildings 1-3 of the Twin Creeks site with
  associated landscaping and infrastructure. Source: Loudoun County land de
 velopment case list\, https://logis.loudoun.gov/gis/rest/services/Projects
 /LOLA_DATA/MapServer/0\, via data/activity.json. Loudoun Data Center Watch
  is an independent community project. It is not affiliated with\, endorsed
  by\, or operated by Loudoun County government\, Erin Brockovich\, or any 
 data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/f9308223
 -9aa3-4fad-a739-ed6ebae98089
CATEGORIES:Site plan
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-d7a7bccb81fe8141a69d@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260724
DTEND;VALUE=DATE:20260725
SUMMARY:New application — site plan: IAD03 Relocation Drive\, Sterling di
 strict
DESCRIPTION:Site plan EPLAN-2026-0105\, filed with Loudoun County on 24 Jul
 y 2026. The county's current status for it is In Review. Located in the St
 erling district\, worked out from the coordinates the county publishes wit
 h the case against data/districts.geojson. The applicant's own description
 : Revision to STMP-2022-0003 and subsequent approved plans SPAM-2022-0072 
 and SPAM-2023-0018 proposing minor changes to curb and gutter\, sidewalks\
 , mechanical yard access. Data Center Source: Loudoun County land developm
 ent case list\, https://logis.loudoun.gov/gis/rest/services/Projects/LOLA_
 DATA/MapServer/0\, via data/activity.json. Loudoun Data Center Watch is an
  independent community project. It is not affiliated with\, endorsed by\, 
 or operated by Loudoun County government\, Erin Brockovich\, or any data c
 enter owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/ceef6aac
 -7c6b-4775-a5b0-3a93a311f079
CATEGORIES:Site plan
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-7f180a7361f681f5a606@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260724
DTEND;VALUE=DATE:20260725
SUMMARY:New application — site plan: Buildings VA13 & 14\, Sterling distr
 ict
DESCRIPTION:Site plan EPLAN-2026-0106\, filed with Loudoun County on 24 Jul
 y 2026. The county's current status for it is In Review. Located in the St
 erling district\, worked out from the coordinates the county publishes wit
 h the case against data/districts.geojson. The applicant's own description
 : Revision to VA14 Site plan to shift the security gate and include a Guar
 d booth with waterline and sanitary Connections (revision to SPAM-2021-006
 5) Data Center Source: Loudoun County land development case list\, https:/
 /logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/0\, via 
 data/activity.json. Loudoun Data Center Watch is an independent community 
 project. It is not affiliated with\, endorsed by\, or operated by Loudoun 
 County government\, Erin Brockovich\, or any data center owner or operator
 .
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/678d08c2
 -01f8-41ce-87f3-e50f575ef7aa
CATEGORIES:Site plan
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-6f9ecb6351c0ac0db6f6@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260715
DTEND;VALUE=DATE:20260716
SUMMARY:New application — site plan: Project Celtic Phases 1 & 2 - Novec 
 Bridging Power\, Leesburg district
DESCRIPTION:Site plan EPLAN-2026-0098\, filed with Loudoun County on 15 Jul
 y 2026. The county's current status for it is In Review. Located in the Le
 esburg district\, worked out from the coordinates the county publishes wit
 h the case against data/districts.geojson. The applicant's own description
 : PROJECT CELTIC PH 1 & 2 BRIDGING POWER - This proposed site plan adds te
 mporary NOVEC electrical power line from north of the project near Cochran
  Mill Road routed through Phases 1 & 2 to a point parallel to Patriot Park
  Drive and terminating on the western side of the existing gas transmissio
 n line Source: Loudoun County land development case list\, https://logis.l
 oudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/0\, via data/act
 ivity.json. Loudoun Data Center Watch is an independent community project.
  It is not affiliated with\, endorsed by\, or operated by Loudoun County g
 overnment\, Erin Brockovich\, or any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/0a055a29
 -899f-4e53-a2dc-921b84df92aa
CATEGORIES:Site plan
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-988e6043839f5f748d9d@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260713
DTEND;VALUE=DATE:20260714
SUMMARY:New application — zoning determination: Data Centers AO\, Leesbur
 g district
DESCRIPTION:Zoning determination ZCOR-2026-0210\, filed with Loudoun County
  on 13 July 2026. The county's current status for it is Approved. Located 
 in the Leesburg district\, worked out from the coordinates the county publ
 ishes with the case against data/districts.geojson. The applicant's own de
 scription: Buddy Rizer of Economic Development is requesting an advisory o
 pinion on the applicability of the February 14\, 2000 Zoning Administrator
  Determination on data center uses today. Source: Loudoun County land deve
 lopment case list\, https://logis.loudoun.gov/gis/rest/services/Projects/L
 OLA_DATA/MapServer/0\, via data/activity.json. Loudoun Data Center Watch i
 s an independent community project. It is not affiliated with\, endorsed b
 y\, or operated by Loudoun County government\, Erin Brockovich\, or any da
 ta center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/ac825658
 -4aaf-4735-8dca-bb24975f6bdd
CATEGORIES:Zoning determination
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-dd2c533a6ccb10dc72a9@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260707
DTEND;VALUE=DATE:20260708
SUMMARY:New application — zoning determination: JK Tech Park No. 1 Vestin
 g DETER\, Little River district
DESCRIPTION:Zoning determination ZCOR-2026-0188\, filed with Loudoun County
  on 7 July 2026. The county's current status for it is Approved. Located i
 n the Little River district\, worked out from the coordinates the county p
 ublishes with the case against data/districts.geojson. The applicant's own
  description: Colleen Gillis from Curata Partners is requesting a Vested R
 ights Determination for PINs 202-28-5740 and 202-26-0981 if data centers a
 re vested rights. Source: Loudoun County land development case list\, http
 s://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/0\, v
 ia data/activity.json. Loudoun Data Center Watch is an independent communi
 ty project. It is not affiliated with\, endorsed by\, or operated by Loudo
 un County government\, Erin Brockovich\, or any data center owner or opera
 tor.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/9c8baa00
 -9134-4759-be83-1af6462d13f2
CATEGORIES:Zoning determination
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-dd3a77d4b4e507c10b44@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260701
DTEND;VALUE=DATE:20260702
SUMMARY:New application — zoning determination: Davis Drive DETER\, Leesb
 urg district
DESCRIPTION:Zoning determination ZCOR-2026-0202\, filed with Loudoun County
  on 1 July 2026. The county's current status for it is Approved. Located i
 n the Leesburg district\, worked out from the coordinates the county publi
 shes with the case against data/districts.geojson. The applicant's own des
 cription: This ZCOR approves minor changes to an approved Special Exceptio
 n for Sterling Park Data Center on Davis Drive\, PINs 033-385671\, 033-38-
 7850 and 033-39-2929 (to be combined under PLAT-2024-0281). Staff finds th
 e requested changes to EPLAN-2023-0089\, as depicted in EPLAN-2026-0086\, 
 are minor changes  Source: Loudoun County land development case list\, htt
 ps://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/0\, 
 via data/activity.json. Loudoun Data Center Watch is an independent commun
 ity project. It is not affiliated with\, endorsed by\, or operated by Loud
 oun County government\, Erin Brockovich\, or any data center owner or oper
 ator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/94150382
 -d78a-400f-b0e3-530886cd14f2
CATEGORIES:Zoning determination
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-6853e35c317d803ce549@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260701
DTEND;VALUE=DATE:20260702
SUMMARY:New application — site plan: Sterling Park\, Leesburg district
DESCRIPTION:Site plan EPLAN-2026-0086\, filed with Loudoun County on 1 July
  2026. The county's current status for it is In Review. Located in the Lee
 sburg district\, worked out from the coordinates the county publishes with
  the case against data/districts.geojson. The applicant's own description:
  Sterling Park - Site plan amendment to switch the location of the buildin
 g with that of the mechanical yard. Data Center Source: Loudoun County lan
 d development case list\, https://logis.loudoun.gov/gis/rest/services/Proj
 ects/LOLA_DATA/MapServer/0\, via data/activity.json. Loudoun Data Center W
 atch is an independent community project. It is not affiliated with\, endo
 rsed by\, or operated by Loudoun County government\, Erin Brockovich\, or 
 any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/bc4b57c3
 -2ada-4514-a004-f7876ca86b96
CATEGORIES:Site plan
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-0cc64de3a1460396a6d7@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260629
DTEND;VALUE=DATE:20260630
SUMMARY:New application — zoning determination: Vantage Data Centers VA16
 \, Sterling district
DESCRIPTION:Zoning determination ZCOR-2026-0196\, filed with Loudoun County
  on 29 June 2026. The county's current status for it is In Review. Located
  in the Sterling district\, worked out from the coordinates the county pub
 lishes with the case against data/districts.geojson. The applicant's own d
 escription: Bria Burke of Cooley LLP (on behalf of the owner) is requestin
 g a minor modification to a SPEX\, EPLAN-2025-0217.\n\nCenters VA16 LLC (t
 he “Owner”)\, to request your office’s confirmation that the minor c
 hanges proposed with\nthe currently in-process data center site plan amend
 ment (EPLAN-2025-0217) for  Source: Loudoun County land development case l
 ist\, https://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapSe
 rver/0\, via data/activity.json. Loudoun Data Center Watch is an independe
 nt community project. It is not affiliated with\, endorsed by\, or operate
 d by Loudoun County government\, Erin Brockovich\, or any data center owne
 r or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/a3144657
 -d69d-4177-90d7-d3c79e99595c
CATEGORIES:Zoning determination
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-dbb9bd9c8916b3344c69@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260626
DTEND;VALUE=DATE:20260627
SUMMARY:New application — special exception: Relocation Drive Data Center
 \, Sterling district
DESCRIPTION:Special exception SPEX-2026-0038\, filed with Loudoun County on
  26 June 2026. The county's current status for it is In Review. Located in
  the Sterling district\, worked out from the coordinates the county publis
 hes with the case against data/districts.geojson. The applicant's own desc
 ription: SEE LEGI-2026-0019 FOR DOCUMENTS\, TIMELINE AND WORKFLOW. Relocat
 ion Drive Data Center-- A Special Exception to permit the redevelopment of
  existing Data Center uses. Source: Loudoun County land development case l
 ist\, https://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapSe
 rver/0\, via data/activity.json. Loudoun Data Center Watch is an independe
 nt community project. It is not affiliated with\, endorsed by\, or operate
 d by Loudoun County government\, Erin Brockovich\, or any data center owne
 r or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/7025cf2e
 -ecd7-4f15-bd52-f1bcfb4872a4
CATEGORIES:Special exception
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-f57b1361561ef51032a7@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260626
DTEND;VALUE=DATE:20260627
SUMMARY:New application — legislative application: Relocation Drive Data 
 Center\, Sterling district
DESCRIPTION:Legislative Application LEGI-2026-0019\, filed with Loudoun Cou
 nty on 26 June 2026. The county's current status for it is In Review. Loca
 ted in the Sterling district\, worked out from the coordinates the county 
 publishes with the case against data/districts.geojson. The applicant's ow
 n description: Relocation Drive Data Center: A Zoning Concept Plan Amendme
 nt and Special Exception to permit the redevelopment of existing Data Cent
 er uses at a 0.86 FAR. Source: Loudoun County land development case list\,
  https://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/
 0\, via data/activity.json. Loudoun Data Center Watch is an independent co
 mmunity project. It is not affiliated with\, endorsed by\, or operated by 
 Loudoun County government\, Erin Brockovich\, or any data center owner or 
 operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/6528f271
 -db35-4566-8f0a-ffd9ddc1aed5
CATEGORIES:Legislative Application
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-8c9b837dbbfcdf2869dc@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260626
DTEND;VALUE=DATE:20260627
SUMMARY:New application — concept plan amendment: Relocation Drive Data C
 enter\, Sterling district
DESCRIPTION:Concept plan amendment ZCPA-2026-0008\, filed with Loudoun Coun
 ty on 26 June 2026. The county's current status for it is In Review. Locat
 ed in the Sterling district\, worked out from the coordinates the county p
 ublishes with the case against data/districts.geojson. The applicant's own
  description: SEE LEGI-2026-0019 FOR DOCUMENTS\, TIMELINE AND WORKFLOW. Re
 location Drive Data Center - A Zoning Concept Plan Amendment and Special E
 xception to permit the redevelopment of existing Data Center uses at a 0.8
 6 FAR. Source: Loudoun County land development case list\, https://logis.l
 oudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/0\, via data/act
 ivity.json. Loudoun Data Center Watch is an independent community project.
  It is not affiliated with\, endorsed by\, or operated by Loudoun County g
 overnment\, Erin Brockovich\, or any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/4a5f85ba
 -e1a1-41e5-aaa9-6759bf0c89e9
CATEGORIES:Concept plan amendment
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-e5e7ef7385123cb6ffd9@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260625
DTEND;VALUE=DATE:20260626
SUMMARY:New application — site plan: Thayer Road\, Sterling district
DESCRIPTION:Site plan EPLAN-2026-0084\, filed with Loudoun County on 25 Jun
 e 2026. The county's current status for it is In Review. Located in the St
 erling district\, worked out from the coordinates the county publishes wit
 h the case against data/districts.geojson. The applicant's own description
 : THAYER RD DATA CENTER SPAM: THIS SPAM IS TO ADJUST THE BUILDING HEIGHT O
 F THE PROPOSED BUILDING FROM 45' TO 65'. NOTE THAT THE SIGNING ENGINEER FO
 R GORDON IS ONLY VALIDATING THE CHANGE IN BUILDING HEIGHT ON THE CLOUDED S
 HEETS IN THE SHEET INDEX ONLY. Amending EPLAN-2024-0058 Source: Loudoun Co
 unty land development case list\, https://logis.loudoun.gov/gis/rest/servi
 ces/Projects/LOLA_DATA/MapServer/0\, via data/activity.json. Loudoun Data 
 Center Watch is an independent community project. It is not affiliated wit
 h\, endorsed by\, or operated by Loudoun County government\, Erin Brockovi
 ch\, or any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/5427faf1
 -ce49-4b55-96be-f089000d8235
CATEGORIES:Site plan
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-b9eac2f1abef6b5ef402@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260617
DTEND;VALUE=DATE:20260618
SUMMARY:New application — site plan: Arcola Grove Data Centers Site Plan\
 , Dulles district
DESCRIPTION:Site plan EPLAN-2026-0083\, filed with Loudoun County on 17 Jun
 e 2026. The county's current status for it is In Review. Located in the Du
 lles district\, worked out from the coordinates the county publishes with 
 the case against data/districts.geojson. The applicant's own description: 
 Site Plan for 2 proposed Data Center buildings\, guard booth and all assoc
 iated infrastructure. Source: Loudoun County land development case list\, 
 https://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/0
 \, via data/activity.json. Loudoun Data Center Watch is an independent com
 munity project. It is not affiliated with\, endorsed by\, or operated by L
 oudoun County government\, Erin Brockovich\, or any data center owner or o
 perator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/5a7a0e23
 -ef2d-4c61-92bc-c652a649da7e
CATEGORIES:Site plan
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-1342ed0f9dac49bfbde1@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260608
DTEND;VALUE=DATE:20260609
SUMMARY:New application — zoning determination: Vantage Data Centers VA31
 \, Ashburn district
DESCRIPTION:Zoning determination ZCOR-2026-0181\, filed with Loudoun County
  on 8 June 2026. The county's current status for it is In Review. Located 
 in the Ashburn district\, worked out from the coordinates the county publi
 shes with the case against data/districts.geojson. The applicant's own des
 cription: Vantage Data Centers VA3 LLC and Vantage Data Centers VA31 LLC (
 the “Owner”)\,  request your office’s confirmation that the minor ch
 anges proposed and already reviewed with staff to approved data center sit
 e plan STMP-2022-0016 are permitted pursuant to Section 10.11.01.H of the 
 Loudoun County Zoning Source: Loudoun County land development case list\, 
 https://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/0
 \, via data/activity.json. Loudoun Data Center Watch is an independent com
 munity project. It is not affiliated with\, endorsed by\, or operated by L
 oudoun County government\, Erin Brockovich\, or any data center owner or o
 perator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/3b3a9aa0
 -b45b-4e35-b21d-57df17dd1d3c
CATEGORIES:Zoning determination
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-cd39dabf0f4e2074437b@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260608
DTEND;VALUE=DATE:20260609
SUMMARY:New application — special exception: Relocation Drive Data Center
 \, Sterling district
DESCRIPTION:Special exception SPEX-2026-0037\, filed with Loudoun County on
  8 June 2026. The county's current status for it is Submitted. Located in 
 the Sterling district\, worked out from the coordinates the county publish
 es with the case against data/districts.geojson. The applicant's own descr
 iption: SEE LEGI-2026-0020 FOR DOCUMENTS\, TIMELINE AND WORKFLOW. Relocati
 on Drive Data Center-A Special Exception to permit the redevelopment of ex
 isting Data Center uses at a 0.86 FAR. Source: Loudoun County land develop
 ment case list\, https://logis.loudoun.gov/gis/rest/services/Projects/LOLA
 _DATA/MapServer/0\, via data/activity.json. Loudoun Data Center Watch is a
 n independent community project. It is not affiliated with\, endorsed by\,
  or operated by Loudoun County government\, Erin Brockovich\, or any data 
 center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/4e7953d4
 -1df0-4fe7-b483-43ff8cd6dd88
CATEGORIES:Special exception
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-1f9345b3c3697996e354@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260603
DTEND;VALUE=DATE:20260604
SUMMARY:New application — site plan: Twin Creeks Buildings 4 & 5\, Leesbu
 rg district
DESCRIPTION:Site plan EPLAN-2026-0078\, filed with Loudoun County on 3 June
  2026. The county's current status for it is In Review. Located in the Lee
 sburg district\, worked out from the coordinates the county publishes with
  the case against data/districts.geojson. The applicant's own description:
  TWIN CREEKS DATA CENTERS: Site containing two data center buildings with 
 associated infrastructure and landscaping. (REVISION OF APPROVED PLAN STPL
 -2022-0040) Source: Loudoun County land development case list\, https://lo
 gis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/0\, via dat
 a/activity.json. Loudoun Data Center Watch is an independent community pro
 ject. It is not affiliated with\, endorsed by\, or operated by Loudoun Cou
 nty government\, Erin Brockovich\, or any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/f128a01d
 -5afc-4b87-a7ef-21a781aa677f
CATEGORIES:Site plan
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-a626db2c6818982abd0b@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260528
DTEND;VALUE=DATE:20260529
SUMMARY:New application — site plan: Site Plan Amendment for NTT Global D
 ata Centers VA\, Broad Run district
DESCRIPTION:Site plan EPLAN-2026-0075\, filed with Loudoun County on 28 May
  2026. The county's current status for it is In Review. Located in the Bro
 ad Run district\, worked out from the coordinates the county publishes wit
 h the case against data/districts.geojson. The applicant's own description
 : Revision associated with this site plan revision include additional floo
 r area for the guard shack booth at the secure entrance to the subject sit
 e per approved site plan STMP-2022-0004. Data Center Source: Loudoun Count
 y land development case list\, https://logis.loudoun.gov/gis/rest/services
 /Projects/LOLA_DATA/MapServer/0\, via data/activity.json. Loudoun Data Cen
 ter Watch is an independent community project. It is not affiliated with\,
  endorsed by\, or operated by Loudoun County government\, Erin Brockovich\
 , or any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/6e3a75ef
 -98c8-4d4b-afe1-b0b473871be4
CATEGORIES:Site plan
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-9b8a83d766da74c11c41@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260522
DTEND;VALUE=DATE:20260523
SUMMARY:New application — gis update: GISU-2026-0041\, Broad Run district
DESCRIPTION:GIS Update GISU-2026-0041\, filed with Loudoun County on 22 May
  2026. The county's current status for it is Submitted. Located in the Bro
 ad Run district\, worked out from the coordinates the county publishes wit
 h the case against data/districts.geojson. The applicant's own description
 : This project is located at the parcel between Leesburg Pike\, Ashburn Vi
 llage Blvd\, and Russell Branch Pkwy in Ashburn\, VA 20147. Scope of devel
 opment includes data center buildings with one substation and improvements
  per applicable proffers. Site access is provided from Ashburn Village Blv
 d and Rus Source: Loudoun County land development case list\, https://logi
 s.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/0\, via data/
 activity.json. Loudoun Data Center Watch is an independent community proje
 ct. It is not affiliated with\, endorsed by\, or operated by Loudoun Count
 y government\, Erin Brockovich\, or any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/0c99ac21
 -2c53-4c2e-977c-d9eb6343b831
CATEGORIES:GIS Update
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-bf68d317d4c0e749b808@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260514
DTEND;VALUE=DATE:20260515
SUMMARY:New application — site plan: Vantage - VA3\, Ashburn district
DESCRIPTION:Site plan EPLAN-2026-0066\, filed with Loudoun County on 14 May
  2026. The county's current status for it is In Review. Located in the Ash
 burn district\, worked out from the coordinates the county publishes with 
 the case against data/districts.geojson. The applicant's own description: 
 Site Plan Amendment to previously approved STMP-2022-0016 and EPLAN-2024-0
 004 proposing revision to reduce building gross floor area\, proposed buil
 ding stories\, BMP facilities and related infrastructure. Data Center Sour
 ce: Loudoun County land development case list\, https://logis.loudoun.gov/
 gis/rest/services/Projects/LOLA_DATA/MapServer/0\, via data/activity.json.
  Loudoun Data Center Watch is an independent community project. It is not 
 affiliated with\, endorsed by\, or operated by Loudoun County government\,
  Erin Brockovich\, or any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/186d42a4
 -4193-4d9c-8edc-1fa67b792521
CATEGORIES:Site plan
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-2eff428bb145fdb8c0f2@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260511
DTEND;VALUE=DATE:20260512
SUMMARY:New application — special exception: Spring Valley Technology Par
 k\, Ashburn district
DESCRIPTION:Special exception SPEX-2026-0031\, filed with Loudoun County on
  11 May 2026. The county's current status for it is In Review. Located in 
 the Ashburn district\, worked out from the coordinates the county publishe
 s with the case against data/districts.geojson. The applicant's own descri
 ption: SEE LEGI-2024-0074 FOR DOCUMENTS\, TIMELINE AND WORKFLOW. SPRING VA
 LLEY TECHNOLOGY PARK: 4.06.02.D.2 Separation from Residential. Ground moun
 ted Data Center Mechanical Equipment must be separated from adjacent prope
 rty that has existing residential development\, an approved CDP or plat or
  plan showing Source: Loudoun County land development case list\, https://
 logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/0\, via d
 ata/activity.json. Loudoun Data Center Watch is an independent community p
 roject. It is not affiliated with\, endorsed by\, or operated by Loudoun C
 ounty government\, Erin Brockovich\, or any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/a45a8c98
 -2a0e-43f1-95f0-4b8f9557cb50
CATEGORIES:Special exception
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-123f8c0c0ce222694a90@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260505
DTEND;VALUE=DATE:20260506
SUMMARY:New application — site plan: Tech Park at Brambleton\, Little Riv
 er district
DESCRIPTION:Site plan EPLAN-2026-0053\, filed with Loudoun County on 5 May 
 2026. The county's current status for it is In Review. Located in the Litt
 le River district\, worked out from the coordinates the county publishes w
 ith the case against data/districts.geojson. The applicant's own descripti
 on: TECH PARK @ BRAMBLETON SPAM: Plan revision to add electrical equipment
  pad and retaining wall. Amending STMP-2022-0018. Data Center Source: Loud
 oun County land development case list\, https://logis.loudoun.gov/gis/rest
 /services/Projects/LOLA_DATA/MapServer/0\, via data/activity.json. Loudoun
  Data Center Watch is an independent community project. It is not affiliat
 ed with\, endorsed by\, or operated by Loudoun County government\, Erin Br
 ockovich\, or any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/bec32476
 -8bce-4deb-a801-ed30b480081f
CATEGORIES:Site plan
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-6a6d29dd9e7bdb1428fd@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260504
DTEND;VALUE=DATE:20260505
SUMMARY:New application — zoning determination: Tech Park at Brambleton\,
  Little River district
DESCRIPTION:Zoning determination ZCOR-2026-0145\, filed with Loudoun County
  on 4 May 2026. The county's current status for it is Approved. Located in
  the Little River district\, worked out from the coordinates the county pu
 blishes with the case against data/districts.geojson. The applicant's own 
 description: Christie Grucella of Bohler Engineering is requesting a minor
  modification to SPEX for Brambleton Tech Park\, EPLAN-2026-0053.\n\nPursu
 ant to Table 3.02.05-1\, Footnote #3\, “Notwithstanding Section 1.02.E.2
 \, a site plan or site plan amendment application for minor changes to an 
 approved site plan for a  Source: Loudoun County land development case lis
 t\, https://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServ
 er/0\, via data/activity.json. Loudoun Data Center Watch is an independent
  community project. It is not affiliated with\, endorsed by\, or operated 
 by Loudoun County government\, Erin Brockovich\, or any data center owner 
 or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/9828c98d
 -4f7f-4f09-87f9-6e7a10e3c004
CATEGORIES:Zoning determination
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-14837a22c562136813b8@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260402
DTEND;VALUE=DATE:20260403
SUMMARY:New application — site plan: Ashburn Crossing Phase V Site Plan A
 mendment\, Broad Run district
DESCRIPTION:Site plan EPLAN-2026-0041\, filed with Loudoun County on 2 Apri
 l 2026. The county's current status for it is In Review. Located in the Br
 oad Run district\, worked out from the coordinates the county publishes wi
 th the case against data/districts.geojson. The applicant's own descriptio
 n: Proposed Site Plan Amendment to previously approved (EPLAN-2024-0024) t
 o revise two storm outfalls that convey runoff from Phase V to the existin
 g pond at the intersection of Gloucester Parkway and Loudoun County Parkwa
 y\, as well as adjust the plantings and tree preservation easement along G
 louceste Source: Loudoun County land development case list\, https://logis
 .loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/0\, via data/a
 ctivity.json. Loudoun Data Center Watch is an independent community projec
 t. It is not affiliated with\, endorsed by\, or operated by Loudoun County
  government\, Erin Brockovich\, or any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/443f8137
 -87a8-4984-98ff-e1f893bc2a88
CATEGORIES:Site plan
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-61dc04e4ea76dc75a895@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260401
DTEND;VALUE=DATE:20260402
SUMMARY:New application — floodplain: Ashburn Data Center Floodplain Alte
 ration\, Sterling district
DESCRIPTION:Floodplain FLPL-2026-0008\, filed with Loudoun County on 1 Apri
 l 2026. The county's current status for it is In Review. Located in the St
 erling district\, worked out from the coordinates the county publishes wit
 h the case against data/districts.geojson. The applicant's own description
 : KIMLEY-HORN HAS PREPARED THIS FLOODPLAIN ALTERATION TO\nDETERMINE THE PR
 OPOSED 100-YEAR FLOOD ELEVATIONS AND EXTENTS WITHIN THE SITE BASED ON THE 
 PROPOSED SITE ALTERATIONS IN\nACCORDANCE WITH THE FACILITIES STANDARDS MAN
 UAL. Source: Loudoun County land development case list\, https://logis.lou
 doun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/0\, via data/activ
 ity.json. Loudoun Data Center Watch is an independent community project. I
 t is not affiliated with\, endorsed by\, or operated by Loudoun County gov
 ernment\, Erin Brockovich\, or any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/264ae2ed
 -dbe5-433e-8255-0bd8a6990483
CATEGORIES:Floodplain
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-d2b40552fe0f5bf877f3@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260331
DTEND;VALUE=DATE:20260401
SUMMARY:New application — site plan: LC9 & LC10 Data Center\, Sterling di
 strict
DESCRIPTION:Site plan EPLAN-2026-0039\, filed with Loudoun County on 31 Mar
 ch 2026. The county's current status for it is In Review. Located in the S
 terling district\, worked out from the coordinates the county publishes wi
 th the case against data/districts.geojson. The applicant's own descriptio
 n: LC9 & LC10 DATA CENTER - CONSTRUCTION OF A TWO (2) 2-STORY DATA CENTER 
 BUILDINGS AND ASSOCIATED INFRASTRUCTURE Source: Loudoun County land develo
 pment case list\, https://logis.loudoun.gov/gis/rest/services/Projects/LOL
 A_DATA/MapServer/0\, via data/activity.json. Loudoun Data Center Watch is 
 an independent community project. It is not affiliated with\, endorsed by\
 , or operated by Loudoun County government\, Erin Brockovich\, or any data
  center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/592bce7c
 -01bb-4c20-8ecf-d96f36d608f6
CATEGORIES:Site plan
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-3838230e923aa96ee1a2@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260309
DTEND;VALUE=DATE:20260310
SUMMARY:New application — floodplain: Clintmar\, Little River district
DESCRIPTION:Floodplain FLPL-2026-0005\, filed with Loudoun County on 9 Marc
 h 2026. The county's current status for it is In Review. Located in the Li
 ttle River district\, worked out from the coordinates the county publishes
  with the case against data/districts.geojson. The applicant's own descrip
 tion: Floodplain Alteration for Clintmar plan. Data Center encompassing 18
 2\,254 sf. Source: Loudoun County land development case list\, https://log
 is.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/0\, via data
 /activity.json. Loudoun Data Center Watch is an independent community proj
 ect. It is not affiliated with\, endorsed by\, or operated by Loudoun Coun
 ty government\, Erin Brockovich\, or any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/7122485c
 -ace9-4f25-aa98-5e659a5f863d
CATEGORIES:Floodplain
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-56cb9040f79ee003f718@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260305
DTEND;VALUE=DATE:20260306
SUMMARY:New application — zoning determination: Terminal Drive Buffer Wai
 ver\, Sterling district
DESCRIPTION:Zoning determination ZCOR-2026-0048\, filed with Loudoun County
  on 5 March 2026. The county's current status for it is In Review. Located
  in the Sterling district\, worked out from the coordinates the county pub
 lishes with the case against data/districts.geojson. The applicant's own d
 escription: Curtis Mason of Gordon is requesting an administrative buffer 
 and Waiver to allow the placement of the required Type C Buffer closer to 
 the proposed data center rather than along two of the three perimeter prop
 erty lines adjacent to the existing stormwater management (SWM) pond. Sour
 ce: Loudoun County land development case list\, https://logis.loudoun.gov/
 gis/rest/services/Projects/LOLA_DATA/MapServer/0\, via data/activity.json.
  Loudoun Data Center Watch is an independent community project. It is not 
 affiliated with\, endorsed by\, or operated by Loudoun County government\,
  Erin Brockovich\, or any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/e933cb94
 -4825-4c72-8b16-7a5a66e10257
CATEGORIES:Zoning determination
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-eabf8ad70da5bbce8b6e@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260305
DTEND;VALUE=DATE:20260306
SUMMARY:New application — commission permit: Loudoun Business Park\, Ster
 ling district
DESCRIPTION:Commission permit CMPT-2026-0010\, filed with Loudoun County on
  5 March 2026. The county's current status for it is In Review. Located in
  the Sterling district\, worked out from the coordinates the county publis
 hes with the case against data/districts.geojson. The applicant's own desc
 ription: LOUDOUN BUSINESS PARK\n\nCMPT-2026-0010: A Commission Permit to p
 ermit a public utility.\n\nCMPT-2025-0008: A Commission Permit to permit a
  public utility.\n\nSPEX-2025-0061: A Special Exception to permit a data c
 enter in the Industrial Park (IP) Zoning District.\n\nSPEX-2025-0072: A Sp
 ecial Exception to pe Source: Loudoun County land development case list\, 
 https://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/0
 \, via data/activity.json. Loudoun Data Center Watch is an independent com
 munity project. It is not affiliated with\, endorsed by\, or operated by L
 oudoun County government\, Erin Brockovich\, or any data center owner or o
 perator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/d1af1ce4
 -1db9-4b24-8d43-e7baf6f57fd9
CATEGORIES:Commission permit
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-b0243c9de2f91f9a6575@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260219
DTEND;VALUE=DATE:20260220
SUMMARY:New application — rezoning application: Glenn Drive North & South
 \, Sterling district
DESCRIPTION:Rezoning application ZMAP-2026-0001\, filed with Loudoun County
  on 19 February 2026. The county's current status for it is In Review. Loc
 ated in the Sterling district\, worked out from the coordinates the county
  publishes with the case against data/districts.geojson. The applicant's o
 wn description: GLENN DRIVE NORTH & SOUTH\n\nZMAP-2024-0002: A Zoning Conv
 ersion in the Route 28 Tax District of 42.3 acres from the Planned Develop
 ment–Industrial Park (PD-IP) Zoning District under the 1972 Zoning Ordin
 ance to the Industrial Park (IP) Zoning District under the Zoning Ordinanc
 e.\n\nSPEX-2024-0010: A Sp Source: Loudoun County land development case li
 st\, https://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapSer
 ver/0\, via data/activity.json. Loudoun Data Center Watch is an independen
 t community project. It is not affiliated with\, endorsed by\, or operated
  by Loudoun County government\, Erin Brockovich\, or any data center owner
  or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/82e9eb8e
 -d0ab-4045-83c1-553c0ca67d7a
CATEGORIES:Rezoning application
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-73721a8fbb5fcd2c1df3@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260211
DTEND;VALUE=DATE:20260212
SUMMARY:New application — zoning determination: Dulles North Industrial P
 ark - Lot 4 DETER\, Sterling district
DESCRIPTION:Zoning determination ZCOR-2026-0037\, filed with Loudoun County
  on 11 February 2026. The county's current status for it is Approved. Loca
 ted in the Sterling district\, worked out from the coordinates the county 
 publishes with the case against data/districts.geojson. The applicant's ow
 n description: Reina Hamayama of Bohler Engineering is requesting a determ
 ination seeking confirmation that pursuant to Section 4.06.02.D.2.d. of th
 e Zoning Ordinance\, the mechanical equipment designed to serve data cente
 r at 45757 Maries Road\, Sterling (the "Property")\, is located in a manne
 r that has no impact o Source: Loudoun County land development case list\,
  https://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/
 0\, via data/activity.json. Loudoun Data Center Watch is an independent co
 mmunity project. It is not affiliated with\, endorsed by\, or operated by 
 Loudoun County government\, Erin Brockovich\, or any data center owner or 
 operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/2b069b62
 -cd1d-4b69-96ea-45f90f8df363
CATEGORIES:Zoning determination
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-9de139c2c5df4c8e0e9d@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260202
DTEND;VALUE=DATE:20260203
SUMMARY:New application — special exception: Spring Valley Technology Par
 k\, Ashburn district
DESCRIPTION:Special exception SPEX-2026-0004\, filed with Loudoun County on
  2 February 2026. The county's current status for it is In Review. Located
  in the Ashburn district\, worked out from the coordinates the county publ
 ishes with the case against data/districts.geojson. The applicant's own de
 scription: See LEGI-2024-0074 for all documents\, timelines and workflow. 
 Special Exception to permit data center use in the IP Zoning District Sour
 ce: Loudoun County land development case list\, https://logis.loudoun.gov/
 gis/rest/services/Projects/LOLA_DATA/MapServer/0\, via data/activity.json.
  Loudoun Data Center Watch is an independent community project. It is not 
 affiliated with\, endorsed by\, or operated by Loudoun County government\,
  Erin Brockovich\, or any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/edbf278e
 -8f42-4976-8412-b7a078e4c9fe
CATEGORIES:Special exception
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-b97909f03edfddbd96bc@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260129
DTEND;VALUE=DATE:20260130
SUMMARY:New application — site plan: DULLES BERRY LC8 DATA CENTER\, Sterl
 ing district
DESCRIPTION:Site plan EPLAN-2026-0014\, filed with Loudoun County on 29 Jan
 uary 2026. The county's current status for it is In Review. Located in the
  Sterling district\, worked out from the coordinates the county publishes 
 with the case against data/districts.geojson. The applicant's own descript
 ion: DULLES BERRY LC8 DATA CENTER - This application is for the revision t
 o approved EPLAN-2024-0093 Dulles Berry LC8 Data Center. Revisions include
  a proposed retaining wall\, revisions to the limits of disturbance\, asso
 ciated grading\, and minor revisions to utilities and tree conservation ar
 eas. Source: Loudoun County land development case list\, https://logis.lou
 doun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/0\, via data/activ
 ity.json. Loudoun Data Center Watch is an independent community project. I
 t is not affiliated with\, endorsed by\, or operated by Loudoun County gov
 ernment\, Erin Brockovich\, or any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/2e79044e
 -36a1-4158-ae16-d7f9f5075bbc
CATEGORIES:Site plan
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-a97ee3e0cd623de32033@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20260107
DTEND;VALUE=DATE:20260108
SUMMARY:New application — zoning determination: 22990 Indian Creek Dr DET
 ER\, Sterling district
DESCRIPTION:Zoning determination ZCOR-2026-0004\, filed with Loudoun County
  on 7 January 2026. The county's current status for it is Approved. Locate
 d in the Sterling district\, worked out from the coordinates the county pu
 blishes with the case against data/districts.geojson. The applicant's own 
 description: Christopher Churmusi of Urban Ltd. on behalf of the owner is 
 requesting a zoning determination for the site plan amendment (EPLAN-2024-
 0178) is proposed to convert the existing flex warehouse use developed per
  STPL-2021-0019 to a data center. As part of this plan\, the existing land
 scaping and buffer Source: Loudoun County land development case list\, htt
 ps://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/0\, 
 via data/activity.json. Loudoun Data Center Watch is an independent commun
 ity project. It is not affiliated with\, endorsed by\, or operated by Loud
 oun County government\, Erin Brockovich\, or any data center owner or oper
 ator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/1b92371c
 -e3cd-4bfa-8355-a4496933b884
CATEGORIES:Zoning determination
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-0958d10b5ca6a93bc395@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20251223
DTEND;VALUE=DATE:20251224
SUMMARY:New application — site plan: Vantage-VA16\, Sterling district
DESCRIPTION:Site plan EPLAN-2025-0217\, filed with Loudoun County on 23 Dec
 ember 2025. The county's current status for it is In Review. Located in th
 e Sterling district\, worked out from the coordinates the county publishes
  with the case against data/districts.geojson. The applicant's own descrip
 tion: This revision proposes updates to storm\, sanitary and water utiliti
 es and profiles as well as other minor updates to post-development BMP cal
 culations and pavement designations. Data Center Source: Loudoun County la
 nd development case list\, https://logis.loudoun.gov/gis/rest/services/Pro
 jects/LOLA_DATA/MapServer/0\, via data/activity.json. Loudoun Data Center 
 Watch is an independent community project. It is not affiliated with\, end
 orsed by\, or operated by Loudoun County government\, Erin Brockovich\, or
  any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/56670324
 -3f16-437c-ad11-b180677f5ad7
CATEGORIES:Site plan
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-550ef23579c49f125ea3@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20251124
DTEND;VALUE=DATE:20251125
SUMMARY:New application — subdivision plat: Allegro North Campus- Buildin
 g 2F Site Plan\, Dulles district
DESCRIPTION:Subdivision plat PLAT-2025-0252\, filed with Loudoun County on 
 24 November 2025. The county's current status for it is Approved. Located 
 in the Dulles district\, worked out from the coordinates the county publis
 hes with the case against data/districts.geojson. The applicant's own desc
 ription: EASMEMENT PLAT FOR ALLEGRO NORTH CAMPUS BLDG 2F: Site Plan for a 
 data center development on approximately 11.19 acres. Consists of approxim
 ately 126\,990 SF of data center (2-story)\, 19\,485 SF of office space (2
 -story)\, and 4\,800 SF of loading dock area (1-story). Source: Loudoun Co
 unty land development case list\, https://logis.loudoun.gov/gis/rest/servi
 ces/Projects/LOLA_DATA/MapServer/0\, via data/activity.json. Loudoun Data 
 Center Watch is an independent community project. It is not affiliated wit
 h\, endorsed by\, or operated by Loudoun County government\, Erin Brockovi
 ch\, or any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/7ef22327
 -766e-48a8-b93c-7e6e8edca55a
CATEGORIES:Subdivision plat
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-c6b0c46df442e32f5f83@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20251110
DTEND;VALUE=DATE:20251111
SUMMARY:New application — special exception: Yondr - Tarring\, Dulles dis
 trict
DESCRIPTION:Special exception SPEX-2025-0128\, filed with Loudoun County on
  10 November 2025. The county's current status for it is In Review. Locate
 d in the Dulles district\, worked out from the coordinates the county publ
 ishes with the case against data/districts.geojson. The applicant's own de
 scription: SEE LEGI-2025-0049 FOR TIMELINE\, WORKFLOW AND DOCUMENTS. YONDR
 -TARRING: A Special Exception to permit a data center use in the General I
 ndustry (GI) Zoning District. Source: Loudoun County land development case
  list\, https://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/Map
 Server/0\, via data/activity.json. Loudoun Data Center Watch is an indepen
 dent community project. It is not affiliated with\, endorsed by\, or opera
 ted by Loudoun County government\, Erin Brockovich\, or any data center ow
 ner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/8f3220a7
 -c97a-4a66-9623-81bbc0accfa0
CATEGORIES:Special exception
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-1bd9912a642966da0bee@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20251110
DTEND;VALUE=DATE:20251111
SUMMARY:New application — legislative application: YONDR-TARRING\, Dulles
  district
DESCRIPTION:Legislative Application LEGI-2025-0049\, filed with Loudoun Cou
 nty on 10 November 2025. The county's current status for it is In Review. 
 Located in the Dulles district\, worked out from the coordinates the count
 y publishes with the case against data/districts.geojson. The applicant's 
 own description: YONDR-TARRING\n\nSPEX-2025-0128: A Special Exception to p
 ermit a data center use in the General Industry (GI) Zoning District\n\nSP
 EX-2025-0144:  A Minor Special Exception to eliminate the berm and fencing
  requirements along a portion of the frontage of Youngwood Lane.\n\nSPEX-2
 026-0018: A Minor Special E Source: Loudoun County land development case l
 ist\, https://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapSe
 rver/0\, via data/activity.json. Loudoun Data Center Watch is an independe
 nt community project. It is not affiliated with\, endorsed by\, or operate
 d by Loudoun County government\, Erin Brockovich\, or any data center owne
 r or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/efe1e279
 -0d35-4320-9295-a158d2c2a332
CATEGORIES:Legislative Application
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-f0f29e47c4deb3401a27@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20251105
DTEND;VALUE=DATE:20251106
SUMMARY:New application — site plan: BELMONT INNOVATION CAMPUS BUILDINGS 
 1\,2 & 5\, Ashburn district
DESCRIPTION:Site plan EPLAN-2025-0195\, filed with Loudoun County on 5 Nove
 mber 2025. The county's current status for it is In Review. Located in the
  Ashburn district\, worked out from the coordinates the county publishes w
 ith the case against data/districts.geojson. The applicant's own descripti
 on: (Conditional Approval) BELMONT INNOVATION CAMPUS BUILDINGS 1\, 2 and 5
  - CONSTRUCTION OF 3 DATA CENTER BUILDINGS WITH ALL ASSOCIATED ACCESS & UT
 ILITIES. Source: Loudoun County land development case list\, https://logis
 .loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/0\, via data/a
 ctivity.json. Loudoun Data Center Watch is an independent community projec
 t. It is not affiliated with\, endorsed by\, or operated by Loudoun County
  government\, Erin Brockovich\, or any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/3576d551
 -1558-42af-8a13-d172b8fd57cf
CATEGORIES:Site plan
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-4fc07b9f710699aff695@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20251030
DTEND;VALUE=DATE:20251031
SUMMARY:New application — zoning determination: ZCOR-2025-0418\, Sterling
  district
DESCRIPTION:Zoning determination ZCOR-2025-0418\, filed with Loudoun County
  on 30 October 2025. The county's current status for it is Approved. Locat
 ed in the Sterling district\, worked out from the coordinates the county p
 ublishes with the case against data/districts.geojson. The applicant's own
  description: ZCOR-2025-0418 finds the revisions described in the request\
 , including the adjustment to the location of a retaining wall\, drive ais
 le and related revisions to the building footprint originally subject to E
 PLAN-2023-0087 allowing a data center use on PIN 045-46-5016\, approved on
  December 2\, 2024\, ca Source: Loudoun County land development case list\
 , https://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer
 /0\, via data/activity.json. Loudoun Data Center Watch is an independent c
 ommunity project. It is not affiliated with\, endorsed by\, or operated by
  Loudoun County government\, Erin Brockovich\, or any data center owner or
  operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/58078fa7
 -0c9a-4b74-b685-52748c54f268
CATEGORIES:Zoning determination
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-4307df94d46c71a34f54@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20251030
DTEND;VALUE=DATE:20251031
SUMMARY:New application — subdivision plat: 1501 Moran Road - AS02 Final 
 Site Plan REVISION\, Sterling district
DESCRIPTION:Subdivision plat PLAT-2025-0241\, filed with Loudoun County on 
 30 October 2025. The county's current status for it is Approved. Located i
 n the Sterling district\, worked out from the coordinates the county publi
 shes with the case against data/districts.geojson. The applicant's own des
 cription: Site Plan Amendment to previously approved EPLAN-2023-0087 which
  is a 42 megawatt data center with the associated infrastructure\, roads\,
  parking\, & utilities. Source: Loudoun County land development case list\
 , https://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer
 /0\, via data/activity.json. Loudoun Data Center Watch is an independent c
 ommunity project. It is not affiliated with\, endorsed by\, or operated by
  Loudoun County government\, Erin Brockovich\, or any data center owner or
  operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/4781f697
 -7588-44e8-af5e-cd2bab047785
CATEGORIES:Subdivision plat
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-43c2b7c44cc852810efe@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20251029
DTEND;VALUE=DATE:20251030
SUMMARY:New application — subdivision plat: H5 Data Center SPAM 2 Easemen
 t Plat\, Sterling district
DESCRIPTION:Subdivision plat PLAT-2025-0240\, filed with Loudoun County on 
 29 October 2025. The county's current status for it is In Review. Located 
 in the Sterling district\, worked out from the coordinates the county publ
 ishes with the case against data/districts.geojson. The applicant's own de
 scription: Easement plat to dedicate and vacate easement associated with t
 he H5 Data Center SPAM 2 EPLAN-2025-0180 Source: Loudoun County land devel
 opment case list\, https://logis.loudoun.gov/gis/rest/services/Projects/LO
 LA_DATA/MapServer/0\, via data/activity.json. Loudoun Data Center Watch is
  an independent community project. It is not affiliated with\, endorsed by
 \, or operated by Loudoun County government\, Erin Brockovich\, or any dat
 a center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/d1953413
 -67c9-4fb5-9649-81c5e1456aa1
CATEGORIES:Subdivision plat
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-fedab7642f11a2a6fe5d@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20251020
DTEND;VALUE=DATE:20251021
SUMMARY:New application — site plan: BELMONT INNOVATION CAMPUS BUILDINGS 
 3 & 4\, Ashburn district
DESCRIPTION:Site plan EPLAN-2025-0184\, filed with Loudoun County on 20 Oct
 ober 2025. The county's current status for it is In Review. Located in the
  Ashburn district\, worked out from the coordinates the county publishes w
 ith the case against data/districts.geojson. The applicant's own descripti
 on: BELMONT INNOVATION CAMPUS BUILDINGS 3 & 4 - Site Plan Amendment for EP
 LAN-2025-0107 to add two sanitary Force Mains\, to add a security fence an
 d gates. To relocate storm sewer structures at the northeast corner and as
 sociated infrastructure. Data Center Source: Loudoun County land developme
 nt case list\, https://logis.loudoun.gov/gis/rest/services/Projects/LOLA_D
 ATA/MapServer/0\, via data/activity.json. Loudoun Data Center Watch is an 
 independent community project. It is not affiliated with\, endorsed by\, o
 r operated by Loudoun County government\, Erin Brockovich\, or any data ce
 nter owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/6103058f
 -380b-46a6-9c0d-ef259ba8590f
CATEGORIES:Site plan
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-80bc0bb6945b34a6a4bc@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20251017
DTEND;VALUE=DATE:20251018
SUMMARY:New application — subdivision plat: Telos Data Center\, Broad Run
  district
DESCRIPTION:Subdivision plat PLAT-2025-0234\, filed with Loudoun County on 
 17 October 2025. The county's current status for it is Approved. Located i
 n the Broad Run district\, worked out from the coordinates the county publ
 ishes with the case against data/districts.geojson. The applicant's own de
 scription: TELOS DATA CENTER (ESMT): Easement Plat Showing Creation and Va
 cation of Various Easements in relation to STPL-2023-0007. Source: Loudoun
  County land development case list\, https://logis.loudoun.gov/gis/rest/se
 rvices/Projects/LOLA_DATA/MapServer/0\, via data/activity.json. Loudoun Da
 ta Center Watch is an independent community project. It is not affiliated 
 with\, endorsed by\, or operated by Loudoun County government\, Erin Brock
 ovich\, or any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/c2988215
 -72b4-42cb-a41c-b3734b812b01
CATEGORIES:Subdivision plat
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-bf0a5d123ca9394c10c1@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20251017
DTEND;VALUE=DATE:20251018
SUMMARY:New application — site plan: Site Plan Amendment for H5 Data Cent
 er\, Sterling district
DESCRIPTION:Site plan EPLAN-2025-0180\, filed with Loudoun County on 17 Oct
 ober 2025. The county's current status for it is In Review. Located in the
  Sterling district\, worked out from the coordinates the county publishes 
 with the case against data/districts.geojson. The applicant's own descript
 ion: Revisions to an approved Data Center Site plan to make minor site des
 ign adjustments to accommodate the updated security gate\, gate equipment 
 and security fence. This plan is associated with EPLAN-2023-0078 Source: L
 oudoun County land development case list\, https://logis.loudoun.gov/gis/r
 est/services/Projects/LOLA_DATA/MapServer/0\, via data/activity.json. Loud
 oun Data Center Watch is an independent community project. It is not affil
 iated with\, endorsed by\, or operated by Loudoun County government\, Erin
  Brockovich\, or any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/7d8f2000
 -1f4e-471b-b6b3-1dcd1e1d6543
CATEGORIES:Site plan
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-9184e866486ebb1539eb@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20251017
DTEND;VALUE=DATE:20251018
SUMMARY:New application — site plan: LC11 & LC12 DATA CENTER\, Broad Run 
 district
DESCRIPTION:Site plan EPLAN-2025-0181\, filed with Loudoun County on 17 Oct
 ober 2025. The county's current status for it is In Review. Located in the
  Broad Run district\, worked out from the coordinates the county publishes
  with the case against data/districts.geojson. The applicant's own descrip
 tion: LC11 & LC12 DATA CENTER - REVISION TO APPROVED STPL-2023-0001.  REVI
 SIONS INCLUDEADDITION OF SECURITY FENCE AND GUARD SHACK\, PAVEMENT/PARKING
  REVISIONS AND MINOR UTILITY REVISIONS. Source: Loudoun County land develo
 pment case list\, https://logis.loudoun.gov/gis/rest/services/Projects/LOL
 A_DATA/MapServer/0\, via data/activity.json. Loudoun Data Center Watch is 
 an independent community project. It is not affiliated with\, endorsed by\
 , or operated by Loudoun County government\, Erin Brockovich\, or any data
  center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/9d299ba0
 -d91a-4354-9d75-459a5f2e4cf7
CATEGORIES:Site plan
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-f3f2e5156fcbff75cf22@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20251001
DTEND;VALUE=DATE:20251002
SUMMARY:New application — special exception: Spring Valley Technology Par
 k\, Ashburn district
DESCRIPTION:Special exception SPEX-2025-0136\, filed with Loudoun County on
  1 October 2025. The county's current status for it is In Review. Located 
 in the Ashburn district\, worked out from the coordinates the county publi
 shes with the case against data/districts.geojson. The applicant's own des
 cription: See LEGI-2024-0074 for all documents\, timelines and workflow. M
 inor Special Exception to Modify Type C Buffer requirements for Utility Su
 bstations along portions of the proposed substation that are adjacent to c
 ompatible data center development Source: Loudoun County land development 
 case list\, https://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA
 /MapServer/0\, via data/activity.json. Loudoun Data Center Watch is an ind
 ependent community project. It is not affiliated with\, endorsed by\, or o
 perated by Loudoun County government\, Erin Brockovich\, or any data cente
 r owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/59d1bd4d
 -3498-4779-8d7f-e6fa2f4a45b7
CATEGORIES:Special exception
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-2b3ab385f2d60598e02e@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20250919
DTEND;VALUE=DATE:20250920
SUMMARY:New application — comprehensive plan amendment: Data Center Stand
 ards and Locations Phase 2\, Leesburg district
DESCRIPTION:Comprehensive Plan Amendment CPAM-2025-0001\, filed with Loudou
 n County on 19 September 2025. The county's current status for it is In Re
 view. Located in the Leesburg district\, worked out from the coordinates t
 he county publishes with the case against data/districts.geojson. The appl
 icant's own description: Comprehensive Plan Amendment Data Centers Standar
 ds and Locations Phase 2 Source: Loudoun County land development case list
 \, https://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServe
 r/0\, via data/activity.json. Loudoun Data Center Watch is an independent 
 community project. It is not affiliated with\, endorsed by\, or operated b
 y Loudoun County government\, Erin Brockovich\, or any data center owner o
 r operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/7d1078e2
 -0844-4382-892b-c903a8d19f3d
CATEGORIES:Comprehensive Plan Amendment
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-a37ffa140d094d77302c@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20250916
DTEND;VALUE=DATE:20250917
SUMMARY:New application — zoning ordinance amendment: Data Center Standar
 ds and Locations Phase 2\, Leesburg district
DESCRIPTION:Zoning Ordinance Amendment ZOAM-2025-0002\, filed with Loudoun 
 County on 16 September 2025. The county's current status for it is In Revi
 ew. Located in the Leesburg district\, worked out from the coordinates the
  county publishes with the case against data/districts.geojson. The applic
 ant's own description: Zoning Ordinance Amendment - Data Center Standards 
 and Locations Phase 2 - For more information and documentation please see 
 CPAM-2025-0001. Source: Loudoun County land development case list\, https:
 //logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/0\, via
  data/activity.json. Loudoun Data Center Watch is an independent community
  project. It is not affiliated with\, endorsed by\, or operated by Loudoun
  County government\, Erin Brockovich\, or any data center owner or operato
 r.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/56295a69
 -f226-4fce-971a-e0d5734e7528
CATEGORIES:Zoning Ordinance Amendment
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-0bca58162b3e4d2f579f@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20250915
DTEND;VALUE=DATE:20250916
SUMMARY:New application — pre-application meeting: Belmont Innovation Cam
 pus - Buildings 1\, 2\, & 5\, Leesburg district
DESCRIPTION:Pre-application meeting PMTG-2025-0197\, filed with Loudoun Cou
 nty on 15 September 2025. The county's current status for it is Approved. 
 Located in the Leesburg district\, worked out from the coordinates the cou
 nty publishes with the case against data/districts.geojson. The applicant'
 s own description: Premeeting to discuss the upcoming submission of a Site
  Plan for Buildings 1\, 2\, & 5 of the Belmont Innovation Campus. Submissi
 on will include 3 data center buildings\, 3 guard booths and the associate
 d infrastructure and drive aisles. Source: Loudoun County land development
  case list\, https://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DAT
 A/MapServer/0\, via data/activity.json. Loudoun Data Center Watch is an in
 dependent community project. It is not affiliated with\, endorsed by\, or 
 operated by Loudoun County government\, Erin Brockovich\, or any data cent
 er owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/ea16d20d
 -a9fc-4710-a202-295e1a0047a0
CATEGORIES:Pre-application meeting
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-dfb1369180c02f0d9606@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20250911
DTEND;VALUE=DATE:20250912
SUMMARY:New application — floodplain: Ashbrook Tech Center Floodplain Stu
 dy\, Broad Run district
DESCRIPTION:Floodplain FLPL-2025-0019\, filed with Loudoun County on 11 Sep
 tember 2025. The county's current status for it is Approved. Located in th
 e Broad Run district\, worked out from the coordinates the county publishe
 s with the case against data/districts.geojson. The applicant's own descri
 ption: This project is located at the parcel between Leesburg Pike\, Ashbu
 rn Village Blvd\, and Russell Branch Pkwy in Ashburn\, VA 20147. Scope of 
 development includes data center buildings with one substation and improve
 ments per applicable proffers. Site access is provided from Ashburn Villag
 e Blvd and Rus Source: Loudoun County land development case list\, https:/
 /logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/0\, via 
 data/activity.json. Loudoun Data Center Watch is an independent community 
 project. It is not affiliated with\, endorsed by\, or operated by Loudoun 
 County government\, Erin Brockovich\, or any data center owner or operator
 .
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/445886e9
 -f1ee-40a0-ac41-a68526c37cbe
CATEGORIES:Floodplain
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-3100245fb2aef65222da@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20250910
DTEND;VALUE=DATE:20250911
SUMMARY:New application — site plan: Corscale VA2 Building 1 SPAM 1\, Bro
 ad Run district
DESCRIPTION:Site plan EPLAN-2025-0152\, filed with Loudoun County on 10 Sep
 tember 2025. The county's current status for it is Approved. Located in th
 e Broad Run district\, worked out from the coordinates the county publishe
 s with the case against data/districts.geojson. The applicant's own descri
 ption: CORSCALE VA2 BLDG 1 (SPAM): Revision to STPL-2022-0012\, a data cen
 ter within the Kincora IP District. Source: Loudoun County land developmen
 t case list\, https://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DA
 TA/MapServer/0\, via data/activity.json. Loudoun Data Center Watch is an i
 ndependent community project. It is not affiliated with\, endorsed by\, or
  operated by Loudoun County government\, Erin Brockovich\, or any data cen
 ter owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/83f915a1
 -bebf-45b9-9937-d424fe4c5e1a
CATEGORIES:Site plan
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-6540a63634673a80bec5@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20250910
DTEND;VALUE=DATE:20250911
SUMMARY:New application — legislative application: LOUDOUN BUSINESS PARK\
 , Sterling district
DESCRIPTION:Legislative Application LEGI-2025-0034\, filed with Loudoun Cou
 nty on 10 September 2025. The county's current status for it is In Review.
  Located in the Sterling district\, worked out from the coordinates the co
 unty publishes with the case against data/districts.geojson. The applicant
 's own description: LOUDOUN BUSINESS PARK\n\nCMPT-2026-0010: A Commission 
 Permit to permit a public utility.\n\nCMPT-2025-0008: A Commission Permit 
 to permit a public utility.\n\nSPEX-2025-0061: A Special Exception to perm
 it a data center in the Industrial Park (IP) Zoning District.\n\nSPEX-2025
 -0072: A Special Exception to pe Source: Loudoun County land development c
 ase list\, https://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/
 MapServer/0\, via data/activity.json. Loudoun Data Center Watch is an inde
 pendent community project. It is not affiliated with\, endorsed by\, or op
 erated by Loudoun County government\, Erin Brockovich\, or any data center
  owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/ae1e6733
 -a50b-4370-9ab1-2eadd49bfe63
CATEGORIES:Legislative Application
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-26506505a7303025ee6f@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20250905
DTEND;VALUE=DATE:20250906
SUMMARY:New application — site plan: 1501 Moran Road - AS02 Final Site Pl
 an REVISION\, Sterling district
DESCRIPTION:Site plan EPLAN-2025-0149\, filed with Loudoun County on 5 Sept
 ember 2025. The county's current status for it is Approved. Located in the
  Sterling district\, worked out from the coordinates the county publishes 
 with the case against data/districts.geojson. The applicant's own descript
 ion: Site Plan Amendment to previously approved EPLAN-2023-0087 which is a
  42 megawatt data center with the associated infrastructure\, roads\, park
 ing\, & utilities. Source: Loudoun County land development case list\, htt
 ps://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/0\, 
 via data/activity.json. Loudoun Data Center Watch is an independent commun
 ity project. It is not affiliated with\, endorsed by\, or operated by Loud
 oun County government\, Erin Brockovich\, or any data center owner or oper
 ator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/123160bd
 -635f-4509-add1-1f241aedca57
CATEGORIES:Site plan
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-fa3ffb09e5217dd59d35@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20250826
DTEND;VALUE=DATE:20250827
SUMMARY:New application — special exception: Equinix Ashburn East\, Sterl
 ing district
DESCRIPTION:Special exception SPEX-2025-0057\, filed with Loudoun County on
  26 August 2025. The county's current status for it is In Review. Located 
 in the Sterling district\, worked out from the coordinates the county publ
 ishes with the case against data/districts.geojson. The applicant's own de
 scription: SEE LEGI-2024-0047 FOR ALL TIMELINE\, WORKFLOW\, AND DOCUMENTS:
  EQUINIX ASHBURN EAST: A Special Exception to permit a data center use in 
 the Industrial Park (IP) Zoning District. Source: Loudoun County land deve
 lopment case list\, https://logis.loudoun.gov/gis/rest/services/Projects/L
 OLA_DATA/MapServer/0\, via data/activity.json. Loudoun Data Center Watch i
 s an independent community project. It is not affiliated with\, endorsed b
 y\, or operated by Loudoun County government\, Erin Brockovich\, or any da
 ta center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/ea5d7f3c
 -7c28-4960-a1a6-b3dd478b864b
CATEGORIES:Special exception
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-ef27ce7d80d9531ec6cb@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20250826
DTEND;VALUE=DATE:20250827
SUMMARY:New application — special exception: Equinix Ashburn East\, Sterl
 ing district
DESCRIPTION:Special exception SPEX-2024-0063\, filed with Loudoun County on
  26 August 2025. The county's current status for it is In Review. Located 
 in the Sterling district\, worked out from the coordinates the county publ
 ishes with the case against data/districts.geojson. The applicant's own de
 scription: SEE LEGI-2024-0047 FOR ALL TIMELINE\, WORKFLOW\, AND DOCUMENTS:
  EQUINIX ASHBURN EAST: A Special Exception to allow data center developmen
 t up to a 1.0 floor area ratio (FAR). Source: Loudoun County land developm
 ent case list\, https://logis.loudoun.gov/gis/rest/services/Projects/LOLA_
 DATA/MapServer/0\, via data/activity.json. Loudoun Data Center Watch is an
  independent community project. It is not affiliated with\, endorsed by\, 
 or operated by Loudoun County government\, Erin Brockovich\, or any data c
 enter owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/6d3e3f3f
 -0fd7-4cf6-80cc-8c1d2e3bf656
CATEGORIES:Special exception
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-f1b09da62146085483db@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20250826
DTEND;VALUE=DATE:20250827
SUMMARY:New application — legislative application: Equinix Ashburn East\,
  Sterling district
DESCRIPTION:Legislative Application LEGI-2024-0047\, filed with Loudoun Cou
 nty on 26 August 2025. The county's current status for it is In Review. Lo
 cated in the Sterling district\, worked out from the coordinates the count
 y publishes with the case against data/districts.geojson. The applicant's 
 own description: EQUINIX ASHBURN EAST: \n\nSPEX-2024-0063: A Special Excep
 tion to allow data center development up to a 1.0 floor area ratio (FAR).\
 n\nSPEX-2025-0057: A Special Exception to permit a data center use in the 
 Industrial Park (IP) Zoning District. Source: Loudoun County land developm
 ent case list\, https://logis.loudoun.gov/gis/rest/services/Projects/LOLA_
 DATA/MapServer/0\, via data/activity.json. Loudoun Data Center Watch is an
  independent community project. It is not affiliated with\, endorsed by\, 
 or operated by Loudoun County government\, Erin Brockovich\, or any data c
 enter owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/04c55665
 -8849-40a3-842f-ee6711fb2790
CATEGORIES:Legislative Application
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-56456bcf4ab034aac4d7@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20250811
DTEND;VALUE=DATE:20250812
SUMMARY:New application — subdivision plat: Farah-Naples Data Center Site
  Plan\, Little River district
DESCRIPTION:Subdivision plat PLAT-2025-0200\, filed with Loudoun County on 
 11 August 2025. The county's current status for it is In Review. Located i
 n the Little River district\, worked out from the coordinates the county p
 ublishes with the case against data/districts.geojson. The applicant's own
  description: This project proposes construction of an approximately 100\,
 000 SF data center\, parking lot and associated utilities to serve the bui
 lding. The total disturbed area is 10.58 AC. Source: Loudoun County land d
 evelopment case list\, https://logis.loudoun.gov/gis/rest/services/Project
 s/LOLA_DATA/MapServer/0\, via data/activity.json. Loudoun Data Center Watc
 h is an independent community project. It is not affiliated with\, endorse
 d by\, or operated by Loudoun County government\, Erin Brockovich\, or any
  data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/219d48ef
 -20b9-4820-905d-9f58b2e59604
CATEGORIES:Subdivision plat
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-083c09bef2c705fddef0@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20250808
DTEND;VALUE=DATE:20250809
SUMMARY:New application — site plan: Greenlin Park\, Leesburg district
DESCRIPTION:Site plan EPLAN-2025-0126\, filed with Loudoun County on 8 Augu
 st 2025. The county's current status for it is In Review. Located in the L
 eesburg district\, worked out from the coordinates the county publishes wi
 th the case against data/districts.geojson. The applicant's own descriptio
 n: GREENLIN PARK: The properties are currently zoned PD-IP\, located in th
 e ariport impact OD\, and is under the 1993 Revised Loudoun County Zoning 
 Ordinance. The properties will be developed into four 1-story data centers
  with a substation and associated improvements. The total disturbed area i
 s 51.62 A Source: Loudoun County land development case list\, https://logi
 s.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/0\, via data/
 activity.json. Loudoun Data Center Watch is an independent community proje
 ct. It is not affiliated with\, endorsed by\, or operated by Loudoun Count
 y government\, Erin Brockovich\, or any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/9063890b
 -3368-4e39-afb4-e2e84fcc13ed
CATEGORIES:Site plan
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-7f6f3fc55d4692358069@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20250804
DTEND;VALUE=DATE:20250805
SUMMARY:New application — subdivision plat: Dulles Electric Data Centers 
 (8399)\, Sterling district
DESCRIPTION:Subdivision plat PLAT-2025-0194\, filed with Loudoun County on 
 4 August 2025. The county's current status for it is In Review. Located in
  the Sterling district\, worked out from the coordinates the county publis
 hes with the case against data/districts.geojson. The applicant's own desc
 ription: DEDI and easements associated with EPLAN-2024-0154 Source: Loudou
 n County land development case list\, https://logis.loudoun.gov/gis/rest/s
 ervices/Projects/LOLA_DATA/MapServer/0\, via data/activity.json. Loudoun D
 ata Center Watch is an independent community project. It is not affiliated
  with\, endorsed by\, or operated by Loudoun County government\, Erin Broc
 kovich\, or any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/0fda6811
 -1bb5-40c8-8788-4e7577bb84c7
CATEGORIES:Subdivision plat
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-8aa23b99c8bb42df5e1b@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20250804
DTEND;VALUE=DATE:20250805
SUMMARY:New application — subdivision plat: Dulles Electric Data Centers 
 (7335)\, Sterling district
DESCRIPTION:Subdivision plat PLAT-2025-0195\, filed with Loudoun County on 
 4 August 2025. The county's current status for it is In Review. Located in
  the Sterling district\, worked out from the coordinates the county publis
 hes with the case against data/districts.geojson. The applicant's own desc
 ription: R-O-W dedication\, creation & vacation of easements on PIN 033-35
 -7335\, 033-35-6754 & 033-36-2355 Source: Loudoun County land development 
 case list\, https://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA
 /MapServer/0\, via data/activity.json. Loudoun Data Center Watch is an ind
 ependent community project. It is not affiliated with\, endorsed by\, or o
 perated by Loudoun County government\, Erin Brockovich\, or any data cente
 r owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/767b726a
 -c97d-42d9-a64c-df4191464b0f
CATEGORIES:Subdivision plat
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-9b6aa1ba7499073ceee2@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20250731
DTEND;VALUE=DATE:20250801
SUMMARY:New application — site plan: CyrusOne Sterling 11 Data Center Pha
 se 2\, Dulles district
DESCRIPTION:Site plan EPLAN-2025-0124\, filed with Loudoun County on 31 Jul
 y 2025. The county's current status for it is Approved. Located in the Dul
 les district\, worked out from the coordinates the county publishes with t
 he case against data/districts.geojson. The applicant's own description: C
 YRUSONE STERLING 11 DATA CENTER - PHASE 2: Revision to the approved plan (
 STMP-2022-0017)  showing electrical & telecom duct banks as well as an upd
 ated loading dock footprint. Source: Loudoun County land development case 
 list\, https://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapS
 erver/0\, via data/activity.json. Loudoun Data Center Watch is an independ
 ent community project. It is not affiliated with\, endorsed by\, or operat
 ed by Loudoun County government\, Erin Brockovich\, or any data center own
 er or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/80779d85
 -dc2b-4387-a968-a5648bb3174b
CATEGORIES:Site plan
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-47c44e7112e4e2ea8351@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20250725
DTEND;VALUE=DATE:20250726
SUMMARY:New application — special exception: EQUINIX ASHBURN NORTH\, Broa
 d Run district
DESCRIPTION:Special exception SPEX-2025-0051\, filed with Loudoun County on
  25 July 2025. The county's current status for it is In Review. Located in
  the Broad Run district\, worked out from the coordinates the county publi
 shes with the case against data/districts.geojson. The applicant's own des
 cription: SEE LEGI-2025-0027 FOR TIMELINE\, WORKFLOW\, AND DOCUMENTS. A Sp
 ecial Exception (SPEX) for Data Center Use. Source: Loudoun County land de
 velopment case list\, https://logis.loudoun.gov/gis/rest/services/Projects
 /LOLA_DATA/MapServer/0\, via data/activity.json. Loudoun Data Center Watch
  is an independent community project. It is not affiliated with\, endorsed
  by\, or operated by Loudoun County government\, Erin Brockovich\, or any 
 data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/9ebadbe9
 -b12e-4cae-b1b9-0793dfc75d95
CATEGORIES:Special exception
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-e7c41d826fdfcaf5778b@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20250725
DTEND;VALUE=DATE:20250726
SUMMARY:New application — legislative application: EQUINIX ASHBURN NORTH\
 , Broad Run district
DESCRIPTION:Legislative Application LEGI-2025-0027\, filed with Loudoun Cou
 nty on 25 July 2025. The county's current status for it is In Review. Loca
 ted in the Broad Run district\, worked out from the coordinates the county
  publishes with the case against data/districts.geojson. The applicant's o
 wn description: EQUINIX ASHBURN NORTH: A Special Exception (SPEX) for Data
  Center Use and a Special Exception to exceed a 0.60 Floor Area Ratio on a
  44-acre property in the Industrial Park (IP) Zoning District. Source: Lou
 doun County land development case list\, https://logis.loudoun.gov/gis/res
 t/services/Projects/LOLA_DATA/MapServer/0\, via data/activity.json. Loudou
 n Data Center Watch is an independent community project. It is not affilia
 ted with\, endorsed by\, or operated by Loudoun County government\, Erin B
 rockovich\, or any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/3eed6673
 -54f6-475c-8d4e-58205523c7c9
CATEGORIES:Legislative Application
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-e607c3fccf56b855d664@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20250709
DTEND;VALUE=DATE:20250710
SUMMARY:New application — special exception: Loudoun Business Park\, Ster
 ling district
DESCRIPTION:Special exception SPEX-2025-0097\, filed with Loudoun County on
  9 July 2025. The county's current status for it is In Review. Located in 
 the Sterling district\, worked out from the coordinates the county publish
 es with the case against data/districts.geojson. The applicant's own descr
 iption: LOUDOUN BUSINESS PARK: A Special Exception for data center use\, a
  Special Exception to increase the FAR up to 0.8\, a Special Exception for
  each utility substation (3)\, and a Commission Permit to permit substatio
 n use. Source: Loudoun County land development case list\, https://logis.l
 oudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/0\, via data/act
 ivity.json. Loudoun Data Center Watch is an independent community project.
  It is not affiliated with\, endorsed by\, or operated by Loudoun County g
 overnment\, Erin Brockovich\, or any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/9513f5a9
 -8179-4bc8-8408-43a49be08e04
CATEGORIES:Special exception
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-f93424274b6dc952c7b8@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20250709
DTEND;VALUE=DATE:20250710
SUMMARY:New application — special exception: Loudoun Business Park\, Ster
 ling district
DESCRIPTION:Special exception SPEX-2025-0061\, filed with Loudoun County on
  9 July 2025. The county's current status for it is In Review. Located in 
 the Sterling district\, worked out from the coordinates the county publish
 es with the case against data/districts.geojson. The applicant's own descr
 iption: SEE LEGI-2025-0034 FOR TIMELINE\, WORKFLOW AND DOCUMENTS: A Specia
 l Exception for data center use. Source: Loudoun County land development c
 ase list\, https://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/
 MapServer/0\, via data/activity.json. Loudoun Data Center Watch is an inde
 pendent community project. It is not affiliated with\, endorsed by\, or op
 erated by Loudoun County government\, Erin Brockovich\, or any data center
  owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/b70c3d91
 -b60e-4700-a40a-9297ec026ee7
CATEGORIES:Special exception
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-1402a836e78e60b0dea9@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20250709
DTEND;VALUE=DATE:20250710
SUMMARY:New application — commission permit: Loudoun Business Park\, Ster
 ling district
DESCRIPTION:Commission permit CMPT-2025-0008\, filed with Loudoun County on
  9 July 2025. The county's current status for it is In Review. Located in 
 the Sterling district\, worked out from the coordinates the county publish
 es with the case against data/districts.geojson. The applicant's own descr
 iption: LOUDOUN BUSINESS PARK: A Special Exception for data center use\, a
  Special Exception to increase the FAR up to 0.8\, a Special Exception for
  each utility substation (3)\, and a Commission Permit to permit substatio
 n use. Source: Loudoun County land development case list\, https://logis.l
 oudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/0\, via data/act
 ivity.json. Loudoun Data Center Watch is an independent community project.
  It is not affiliated with\, endorsed by\, or operated by Loudoun County g
 overnment\, Erin Brockovich\, or any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/ec1606e2
 -f0d1-46ca-b4df-184cd6bf7280
CATEGORIES:Commission permit
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-6877388a3d6154088081@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20250618
DTEND;VALUE=DATE:20250619
SUMMARY:New application — special exception: Horseshoe Drive\, Sterling d
 istrict
DESCRIPTION:Special exception SPEX-2025-0055\, filed with Loudoun County on
  18 June 2025. The county's current status for it is In Review. Located in
  the Sterling district\, worked out from the coordinates the county publis
 hes with the case against data/districts.geojson. The applicant's own desc
 ription: HORSESHOE DRIVE: A Special Exception to allow for a 1.0 floor are
 a ratio (FAR) of data center uses. Source: Loudoun County land development
  case list\, https://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DAT
 A/MapServer/0\, via data/activity.json. Loudoun Data Center Watch is an in
 dependent community project. It is not affiliated with\, endorsed by\, or 
 operated by Loudoun County government\, Erin Brockovich\, or any data cent
 er owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/7456913b
 -eb9f-47aa-85b7-1ed75aa21108
CATEGORIES:Special exception
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-270b8c86ae5286f2455e@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20250618
DTEND;VALUE=DATE:20250619
SUMMARY:New application — special exception: Cochran Tech Park\, Leesburg
  district
DESCRIPTION:Special exception SPEX-2025-0054\, filed with Loudoun County on
  18 June 2025. The county's current status for it is In Review. Located in
  the Leesburg district\, worked out from the coordinates the county publis
 hes with the case against data/districts.geojson. The applicant's own desc
 ription: COCHRAN TECH: See LEGI-2024-0037 for all timelines\, document\, a
 nd updates. A Special Exception to allow a data center development on mode
 rately steep slopes in the IP Zoning District. Source: Loudoun County land
  development case list\, https://logis.loudoun.gov/gis/rest/services/Proje
 cts/LOLA_DATA/MapServer/0\, via data/activity.json. Loudoun Data Center Wa
 tch is an independent community project. It is not affiliated with\, endor
 sed by\, or operated by Loudoun County government\, Erin Brockovich\, or a
 ny data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/7cc3cbed
 -094e-421e-8fe6-46f2dca0905c
CATEGORIES:Special exception
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-1f0bc785f258d0784420@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20250618
DTEND;VALUE=DATE:20250619
SUMMARY:New application — site plan: Prologis Park Building 4\, Dulles di
 strict
DESCRIPTION:Site plan EPLAN-2025-0102\, filed with Loudoun County on 18 Jun
 e 2025. The county's current status for it is In Review. Located in the Du
 lles district\, worked out from the coordinates the county publishes with 
 the case against data/districts.geojson. The applicant's own description: 
 THE SUBJECT OF THIS APPLICATION CONSISTS OF THE DESIGN OF A 1-STORY DATA C
 ENTER BUILDING AND ASSOCIATED UTILITIES AND INFRASTRUCTURE. Source: Loudou
 n County land development case list\, https://logis.loudoun.gov/gis/rest/s
 ervices/Projects/LOLA_DATA/MapServer/0\, via data/activity.json. Loudoun D
 ata Center Watch is an independent community project. It is not affiliated
  with\, endorsed by\, or operated by Loudoun County government\, Erin Broc
 kovich\, or any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/a35c87a7
 -96f0-4874-aac6-4e5b4bf827cf
CATEGORIES:Site plan
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-cd0d681b2c20bf6215bd@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20250605
DTEND;VALUE=DATE:20250606
SUMMARY:New application — zoning determination: Sterling Technology Park 
 DETER\, Sterling district
DESCRIPTION:Zoning determination ZCOR-2025-0279\, filed with Loudoun County
  on 5 June 2025. The county's current status for it is Approved. Located i
 n the Sterling district\, worked out from the coordinates the county publi
 shes with the case against data/districts.geojson. The applicant's own des
 cription: Adjustment of Buffer Type C for Data Center use associated with 
 EPLAN-2025-0027 (Section 4.06.02.D.11.a.2 & Section 7.04.03.D.2)\n\nChase 
 Allen of Urban\, Ltd. is requesting a zoning determination for the norther
 n landscape buffers for the Sterling Technology Park site plan at 22400 Sh
 aw Road\, Sterling Source: Loudoun County land development case list\, htt
 ps://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/0\, 
 via data/activity.json. Loudoun Data Center Watch is an independent commun
 ity project. It is not affiliated with\, endorsed by\, or operated by Loud
 oun County government\, Erin Brockovich\, or any data center owner or oper
 ator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/91e6a2d8
 -3b3a-42c9-96d2-3afeb7442d59
CATEGORIES:Zoning determination
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-9a23a2fadcf8f775ef81@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20250527
DTEND;VALUE=DATE:20250528
SUMMARY:New application — zoning determination: True Noth Data Center Inf
 ormal PROF\, Little River district
DESCRIPTION:Zoning determination ZCOR-2025-0261\, filed with Loudoun County
  on 27 May 2025. The county's current status for it is Approved. Located i
 n the Little River district\, worked out from the coordinates the county p
 ublishes with the case against data/districts.geojson. The applicant's own
  description: Hilary Russo of B&D is requesting an informal proffer determ
 ination for a conservation easement plat (PLAT-2025-0145)  that is pursuan
 t to Proffer VII.J of ZCPA-2020-0003\, True North Data. Source: Loudoun Co
 unty land development case list\, https://logis.loudoun.gov/gis/rest/servi
 ces/Projects/LOLA_DATA/MapServer/0\, via data/activity.json. Loudoun Data 
 Center Watch is an independent community project. It is not affiliated wit
 h\, endorsed by\, or operated by Loudoun County government\, Erin Brockovi
 ch\, or any data center owner or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/96821f95
 -2d86-489f-ba99-bf20a64e1ddc
CATEGORIES:Zoning determination
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-caca0cd959c2cac2cc1d@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20250519
DTEND;VALUE=DATE:20250520
SUMMARY:New application — subdivision plat: Dulles Berry LC8 Data Center\
 , Leesburg district
DESCRIPTION:Subdivision plat PLAT-2025-0140\, filed with Loudoun County on 
 19 May 2025. The county's current status for it is Approved. Located in th
 e Leesburg district\, worked out from the coordinates the county publishes
  with the case against data/districts.geojson. The applicant's own descrip
 tion: Bluebeam session # 981-200-327   DULLES BERRY LC8 DATA CENTER: THIS 
 SPAM IS FOR THE REVISION TO CONDITIONALLY APPROVED STMP-2022-0009 LC8 DATA
  CENTER.  REVISIONS INCLUDE MINOR CHANGES TO THE BUILDING FOOTPRINT\, GRAD
 ING\, UTILITIES AND PARKING. Source: Loudoun County land development case 
 list\, https://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapS
 erver/0\, via data/activity.json. Loudoun Data Center Watch is an independ
 ent community project. It is not affiliated with\, endorsed by\, or operat
 ed by Loudoun County government\, Erin Brockovich\, or any data center own
 er or operator.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/92db574c
 -0b16-4b16-bb8d-f1d319cbe57a
CATEGORIES:Subdivision plat
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ldcw-case-236e1dbcf214843d3ab0@loudoundatacenterwatch.org
DTSTAMP:20261120T145829Z
DTSTART;VALUE=DATE:20250513
DTEND;VALUE=DATE:20250514
SUMMARY:New application — zoning determination: Prologis Park Building 4\
 , Dulles district
DESCRIPTION:Zoning determination ZCOR-2025-0238\, filed with Loudoun County
  on 13 May 2025. The county's current status for it is Approved. Located i
 n the Dulles district\, worked out from the coordinates the county publish
 es with the case against data/districts.geojson. The applicant's own descr
 iption: Alex Sarant of Gordon is requesting a zoning determination for the
  construction of additional GFA on an existing data center parcel at 23825
  Erins Run Drive\, Sterling .\n\n8/21/2025\nIt is determined and confirmed
  that the additional data center building #4 you\ndescribe in your request
  can be added to  Source: Loudoun County land development case list\, http
 s://logis.loudoun.gov/gis/rest/services/Projects/LOLA_DATA/MapServer/0\, v
 ia data/activity.json. Loudoun Data Center Watch is an independent communi
 ty project. It is not affiliated with\, endorsed by\, or operated by Loudo
 un County government\, Erin Brockovich\, or any data center owner or opera
 tor.
URL:https://loudouncountyvaeg.tylerhost.net/prod/selfservice#/plan/78e5e015
 -11c3-4e8e-8991-ef950849392a
CATEGORIES:Zoning determination