2022
Supervisors knew what could replace the homes
In 2022, a residential developer was seeking approval to build up to 779 homes at the site, a project called Hyde Park. In his September district update, Supervisor Mike Turner publicly warned that a data center developer could take over the site under the existing office-park zoning if the housing plan fell through.
Read Turner’s warning
The district update explains how the land’s zoning could allow a data center if the housing plan failed.
September 18, 2022 district update ↗
Sept.–Dec. 2022
The Board pushed the housing vote back
At the September hearing, supervisors were already asking about noise, high-voltage power lines and a possible substation. Turner moved to push the housing decision to October, Supervisor Sylvia Glass seconded him, and the motion passed 8–1, with Chair Phyllis Randall opposed.
The residential developer requested more delays, and in December Randall announced another postponement at the developer’s request.
Read the deferral records
Dec. 2022–Jan. 2023
The land changed hands
The land changed hands on December 20 while the housing plan was still pending. The residential developer withdrew it in January, and CyrusOne announced its purchase on January 18. The Board never took a final vote on the homes.
Read the sale and withdrawal records
March 18, 2025
The Board voted to keep the old rules
The Board had two more chances to put these projects under greater public scrutiny. When Loudoun tightened its data center rules in 2025, the Board voted 5–4 to let qualifying projects already in the pipeline keep using the old rules. Randall backed that exception. Turner and Glass voted against it.
Read the grandfathering vote
October 6, 2026
The Board shelved an independent audit
In October 2026, Randall, Turner and Glass all joined the 7–2 majority that shelved an independent audit. The audit would have checked whether listed projects without building permits still qualified for the exception.
Read the audit motion and vote